-
Recent Posts
Archives
Categories
Category Archives: PMI
Actual start and finish date with material Resources in MS PROJECT 2013! When it does make a sense, and when it does not!
Hi, in this Blog Post I will show you how to use Actual Start and Finish date with Material Resources in a proper way. Of course, using MS PROJECT 2013! First I’m going to create brand new Project: As you … Continue reading
When and why assign Resources to Summary Tasks and Milestones in MS PROJECT 2013!
Hi, I got a question from one of my Blog Readers: “Hi, would you be so kind and explain when to assign Resource to Summary Task or Milestone!” I will explain how to do it (which is very easy), and … Continue reading
Manually Scheduled Summary Tasks, and Subtasks in MS PROJECT 2013
Hi, Today I will explain how to use Manually Scheduled Summary Tasks and its Subtasks in MS PROJECT 2013 First I will create new Project, and then I will create one Manually Scheduled Summary Task, like in picture below: Now … Continue reading
Maximal Units and Default Values in MS PROJECT 2013
Hi, my Blog Reader is in trouble. He wrote:”Hi Nenad, I am in need of a favor from you. I am currently working with the MS project to accomplish the team utilization and also to forecast the team’s availability. I … Continue reading
Multiple Critical Paths in MS PROJECT 2013
Hi, today I will show you how to use Option: Calculate multiple critical paths in MS PROJECT 2013! What is Critical Path indeed? This is the longest path which show you how long will a Project Duration be. It is … Continue reading
Status Date line in MS Project 2013!
Hi, I’ve got a simple question from one of my Blog readers: “Hi, in your examples I can see Status Date in a Gantt Chart View. But I can not see it in my Projects. How to get this?” The … Continue reading
Split in progress Task option in MS PROJECT 2013!
Hi, My very good friend Ben Howard, find a problem, and a solution. I will share it with you. But before you continue to read this Post please taka a look on his great site: http://www.applepark.co.uk. Do I have to … Continue reading
Duration with different Resources working time in MS PROJECT 2013!
Hi, with permission of my MVP friend Gérard Ducouret I will explain how different Resources working time affect Task duration in MS Project 2013! I will show you on the example. First, I will create (as I always do), the … Continue reading
Updating Project to status date versus Leveling in MS PROJECT 2013
Hi, yesterday I was teaching one of my Blog Readers about Leveling and Updating Projects in MS PROJECT 2013. The main problem was that after updating Project over allocated resources are still over allocated. I will explain the difference between … Continue reading
Critical Path in Timeline View with MS PROJECT 2013!
Hi, there is a question from one MS PROJECT user: “Hi! In the MS PROJECT 2013, is it possible to have the critical path displayed in the timeline View?” This Post will be short, because it is easy to do … Continue reading