-
Recent Posts
Archives
Categories
Category Archives: PMI
How to Move Project when Project has Manually Scheduled Tasks and/or Constraints in MS PROJECT 2013
Hi, I’ll how you how to move Project when it has Manually Scheduled Tasks or Constraints in MS PROJECT 2013 First I will make a simple Project with no manually Scheduled Tasks or Constraints. Now suppose that your plan is … Continue reading
Status date in “what if” scenario, or how to make our Projects actual data up to date in MS PROJECT 2013
Hi, my Blog reader has a “problem”: “Nenad, thank you for replay! Ok, my be I wasn’t clear with my question… Let me explain my self one more time. Perhaps I’m working on some project, it has 28 task with … Continue reading
How to update Baseline and Save actual data in MS PROJECT 2013?
Hi, I have a question from my Blog reader: “Hi, How can I update Baseline with new Tasks if Project has Tasks with Actual data, e.g I don’t want to loose those actual data, nor I want to change Baseline … Continue reading
Baseline and Overtime work in MS PROJECT 2013
Hi, as usual I have a question from one of my Blog Readers: “Dear Sir, Can you help me to solve one issue in MS Project? After finishing base line work hours, values entered to actual over time not adding … Continue reading
How to add exception into Resource Calendar in MS PROJECT 2013?
Hi, here is question form one of my Blog Readers: “I want assign a task to a particular resource on a Holiday. How can I do that. For eg: I have specified December 25 th as exception in my project … Continue reading
Actuals and Variances with Material Resources in MS PROJECT 2013! – Part 2
Hi, In my previous Post I wrote: “Dear Nenad, I have a doubt in MS Project updation and tracking of material resources. For example, i have budgeted quantity of cement as 100bags but in actual site construction the quantity consumed … Continue reading
Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project 2013 - Preview, MS PROJECT 2010, PMI, PRoject Management
Tagged Microsoft Project 2010, Microsoft Project 2010 - RESOURCES, Microsoft Project 2013, Microsoft Project 2013 - Resources, MS PROJECT - Resources
4 Comments
Task are not Scheduled as expected in MS PROJECT 2013
My Blog reader has a problem: “Hi Nenad. I am creating a simple Project with four Tasks. Task 1 is predecessor for Task 2, etc. I do not have a right Schedule, and they all start at the same date. … Continue reading
Custom duration and date fields in MS PROJECT 2013
Here is a question form one of my Blog Readers: “I have another possible bug in MSP 2013. Try this oneInsert Date1, Insert Duration1, Insert Date2. Now go to custom fields and make date2 a formula [(date1)+(duration1). The obvious answer … Continue reading
Scheduled Duration, Start and Finished Date in MS PROJECT 2013
Hi, A question from my Blog reader is: “Please clarify the purpose of fields Schedule Duration, Schedule Start & Schedule Finish. In which context they are used and how they differ from Duration, Start & Finish Fields ?” I will … Continue reading
Reordering Tasks in Master Project with MICROSOFT PROJECT 2013!
Hi, again one of my Blog Readers has a question: “What if I want to make changes to the master project but don’t want it to change the sub projects? I want to be able to re-order the tasks in … Continue reading