How to apply same filter on different tables in MS PROJECT 2019

Hi,

today I will show you how to apply same filter only once, and use different tables in MS PROJECT 2019.

First, I’m going to create a simple Project:

image

and I will create Resources needed for the Project:

image

Finally I will assign Resources to Tasks:

image

Finally I will save the Baseline:

image

and:

image

Now I want to see some information for all John’s Tasks.

I will apply filter:

image

and I will get:

image

Now let’s say that I want to see Cost, and Work Tables for John. I have two possibilities.

First one is to leave this filter on, and just jump to the Cost and Work Table:

image

and the result is:

image

For the Work Table, the result is:

image

Advantage of this approach is that you have to set filter only once, and no matter which table will you choose, the result will be shown for that file which was applied on another table. Disadvantage is that you do not see filter on other tables (in my example, Cost and Work), and when you want to switch this filter off, you should go to the original table like this:

image

Second possibility is to add a column on each table on which you want to apply filter like this:

image

Now you can apply filter like I did (shown on few pictures above).

Advantage of this approach is that you see filters on each and every table. Disadvantage is that you have to put column on the screen for every table you want to see, and apply filter, and than apply that filter.

BUT! No matter which approach you will take, when you apply filter on one Table it will be shown on any other table which you will look at. And, if you save your project with filter turned on, when you, ore someone else open the same Project again, the filter remains applied.

Regards!

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT 2019 and tagged , . Bookmark the permalink.

Leave a comment