Color indicators for Finish date in Microsoft Project for the Web

Hi,

Today I will show you color indicators for Finish date in Microsoft Project for the Web!

First I will create simple Project with five Tasks:

image

Current date is 05/10/2020, as you can see in Timeline View:

image

In a Grid View I will add two columns: Start and Finish, and I will get:

image

All Tasks have the same Start date, and it is Project Start date which is 05/04/2020.

  • Task 1 has 1 day Duration, and Finish date is 05/04/2020. Since today is 05/10/2020, this task is late, and Finish date is marked red
  • Task 2 has 5 days Duration, and Finish date is 05/08/2020. Since today is 05/10/2020, this task is late, and Finish date is marked red
  • Task 3 has 6 days Duration, and Finish date is 05/11/2020. Since today is 05/10/2020, and finish date is soon, this task is not late, but it should be completed soon, so it is marked yellow
  • Task 4 has 7 days Duration, and Finish date is 05/12/2020. Since today is 05/10/2020, and finish date is soon, this task is not late, but it should be completed soon, so it is marked yellow
  • Task 5 has 8 days Duration, and Finish date is 05/13/2020. Since today is 05/10/2020, and finish date is not so soon, this task is not late, and it is not marked in any color, so it means it’s status is good.

If current date is, for example 05/04/2020, then Task 1 will be marked yellow, but it’s finish date will not be shown as 05/04/2020, but it will be Today.

To conclude:

  • If finish date is not marked (e.g. it’s background is white) – the Task is in good shape
  • If finish date is marked yellow (e.g. it’s background is yellow) – the Task is still in good shape, but you should take care of it, because it can soon be in trouble, e.g. late Tasks
  • If finish date is marked red (e.g. it’s background is red) – the Task is not in good shape, and it means only two things: either you did not put % completed, or Effort completed (e.g. progress), or the Task is late.

Regards

Posted in Microsoft Project for the Web, Project for the Web | Tagged | Leave a comment

Driving Tasks in Microsoft Project for the Web

Hi,

Today, I will show you how can you see driving Tasks in Microsoft Project for the Web.

First I will crate new Project:

image

As you can see, Task 3 has two Predecessors: Task 1, and Task 2. If I look at the Task3 Details, I will see:

image

On the Task’s detail page I can see all Predecessor Tasks, and also I can find information of which Task, or Tasks are “drivers”. In my example, Task 2 is Driving Task, because it determines the “schedule”, or in other words, it determines Start Date of it Successor (Task 3).

If I change Duration of the Task 1 to 5 days, for example, I will get:

image

As you can see now, Task 1 has become the Driving Task, because it determines Start Date of Task 3!

Finally, if I change both, Task 1 and Task 2 duration to, for example 4 days, I will get:

image

As you can see, now both Tasks (1 and 2) are Drivers for The Task 3, as you can see on the picture above.

Simple, and useful!

Regards!

Posted in Microsoft Project for the Web, Project for the Web, PRoject Management | Tagged | Leave a comment

Task constraints in Microsoft Project for the Web

Hi,

as you already know, in Microsoft Project online or desktop version there are lot Task constraints (for example: Start No Earlier Than, Finish No Earlier Than, Must Start On, Must Finish On, etc.) In Microsoft Project for the Web you can find only two Task Constraints: Start No Earlier Than (SNET), and Finish No Earlier Than (FNET), and both of them are Semi Flexible Constraint type.

Let me show you those constraints. First (as always) I will create simple Project with three Tasks:

image

Let’s see how does it look at the Timeline View:

image

Now, I will put 5/14/2020 as Task 2 Start Date:

image

If I hoover my mouse over Strat Date I will see:

image

the little “star” in the right corner shows that it is constraint for the Start date. Now if I click on that date I will see:

image

here I can see “warning message” about constraint, and I can click on the button “Remove Constraint”, and it will be removed, so the Start Date will be set As Soon As Possible (know as flexible constraint). I will not do it for now.

Now I will set Finish date for Task 3 as 5/26/2020, and I will get:

image

As you can see Start date has been changed so duration remains 4 days!

Now I will change Duration for Task 1 to 1 day, and I will get:

image

As you can see Task 2 has the same Start Date, because it cannot be started before 5/14/2020.

I will change Duration for Task 2 to 1 day as well, and I will get:

image

As you can see Task 3 has the same finish Date, because it cannot be finished before 5/26/2020.

Finally I will change Duration for Task 1 to 10 days, and I will get:

image

Now, Start date for the Task 2, and finish Date for the Task 3 are changed, because those date are later than previous ones. And since they have No earlier constraint, it means that both of them can start and finish later.

Regards!

Posted in Microsoft Project for the Web, Project for the Web, PRoject Management | Tagged | Leave a comment

How to get Project for the Web information in Microsoft Dynamics 365

Hi,

today I will show you how can you get information about your Projects for the Web in Microsoft Dynamics 365.

I will create two Projects:

image

As you can see, Project is going to Start at 5/4/2020 and to Finish at 5/8/2020. Total effort is 32 hours. I will say that Task A is 100% completed:

image

Now I will create Second Project:

image

As you can see, Project is going to Start at 5/4/2020 and to Finish at 5/9/2020. Total effort is 56 hours. I will say that Tasks D and E are 100% completed:

image

OK! Now I will switch to Dynamics 365:

SNAGHTML10d5d33f

and:

image

I can find a lot of information for my projects like: Start and finish date, Effort Total, and Effort completed, and % completed of the whole Project. If I click on particular Project like, for example, First Project I will get:

image

If I choose Summary Tab, I will have all information about the whole Project (start date, End Date, Effort and Completed effort), and I also can choose Tasks Tab, and I will get:

image

and here is the same View like when I’m using Project for the Web!

This is very powerful, and I encourage you to use it whenever possible, because here you will find a lot of useful overall information about you Projects!

Regards!

Posted in Microsoft Project for the Web, PMI, PRoject Management | Tagged | Leave a comment

How to setup nonworking days for Resource in Project for the Web?

Hit,

Today I will show you how to setup nonworking days in Project For the Web.

Firs of all, I will assume that my Particular Resource has setup working time. I will open Dynamics 365:

image

and then:

image

I will choose Jim, and I will check his Work Hours:

image

and I will get:

image

Now, suppose that Jim will not work at May 1st since it will celebrate the Labor Day. To make this exception I will mark this date as Time off:

image

and:

image

and, finally I will get:

image

Now, I will create new Project:

image

Task has 5 days Duration, and it will start at the first day of My Project (e.g. Apr 27), and it will be finished at Friday, May 1st.

Now I will assign Jim to this Task, and I will get:

image

As you can see Finish date is now Monday, May 4th, because Jim will not work at May 1st, nor is he working at weekend.

And that’s it!

Regards!

Posted in Microsoft Project for the Web, Project for the Web | Tagged | Leave a comment

“Guest” resources in Project for the Web

Hi,

today I will show you how to use “guest” resources in Project for the web.

First of all, who are guests?. In my Project I can assign resources which are part of my AAD (Azure Active Directory), e.g. users which may have access for Project for the web, and also edit Tasks, schedule or anything else in My Project. And, as you know, when I assign first user to the Task, I can choose between Groups which I want to use.

So, let’s create new Project with two Tasks:

image

Now I will assign Ellen to Task 1:

image

and when I hit Enter, I will get:

image

so, after I confirm that I want to create a new Group, I will have:

image

Now, let’s assume that on John Wayne will be working on Task 2, but he is not in my AAD, he is not supposed to work with Project for he web, and the only thing he would do will be – working on Task 2. To get that I should go to Dynamics 365:

image

and then:

image

and now I will add John Wayne:

image

then I will select Contact as User Type:

image

and now I’m ready to add it like this:

image

and:

image

as you can see, there is a lot of information which I can put, but for this post, all I need is First and last name. After I finish I have to save it once again:

image

Now. I will go back to my Project, and I will add John Wayne to my Task 2:

image

and, finally, I will have:

image

as Simple as that.

To conclude, I will use Contacts as resources for all human resources which are needed to work on some Tasks, but are not regular users, e.g. in AAD!

Regards.

Posted in Microsoft Project for the Web, PMI, PRoject Management | Tagged | Leave a comment

How to customize Working Time for particular Resource in Microsoft Project for the Web?

Hi,

today I sill show you hot to customize Calendar and working time for Particular Resource in Microsoft Project for the Web.

First of all, create your own Calendar Template, according to your Time Zone! Let’s say that my Calendar template should be from 09:00 AM to 05:00 PM, and Time Zone will be GMT+1 (Zagreb time, my hometown). To do that I should follow next steps:

Step 1: Go to Dynamics 365

image

Step 2: Choose – Project

image

Step 3: Choose – Resources

image

Step 4: Add New Generic Resource and choose appropriate Time Zone

image

Step 5: 6  Choose Show Work Hours:

image

Step 6: Go to (for example) 01/01/2020 and click on this date:

image

Step 7: Choose Entire recurring weekly schedule from Start to end:

image

Step 8: Choose Actions-Delete Calendar

image

Step 9: Confirm Deletion

image

Step 10: Go to Set UP and Choose New Weekly Schedule

image

Step 11: Uncheck Saturday and Sunday, and click on the Set Work Hours:

image

Step 12: Choose from 09 AM to 05 PM:

image

Step 13: I will Save and Close Work Schedule Screen:

SNAGHTML13ec1ab5

Step 14: Choose – Setting

image

Step 15: Choose Calendar Templates

image

Step 16: Add new Calendar Template, and for the Template Resource choose the Resource created in Step 4:

image

Now, suppose that I want for one of my resources to have working time from 09:00 AM to 13:00 PM. To set this up I should follow next steps:

Step 1: I will choose one of my Resources, and I will check if he/she has appropriate Time Zone and I will choose Show Work Hours:

image

Step 2: Go to (for example) 01/01/2020 and click on this date:

image

Step 3: Choose Entire recurring weekly schedule from Start to end:

image

Step 4: Choose Actions-Delete Calendar

image

Step 5: Confirm Deletion

image

Step 6: Go to Set UP and Choose New Weekly Schedule

image

Step 7: Uncheck Saturday and Sunday (Jim is not going to work during Weekends), and click on the Set Work Hours:

image

Step 8: Since I want Tim to work from 09 AM to 01 PM I will put those to Start and End:

image

Step 9: I will Save and Close Work Schedule Screen:

image

Now, since everything is Set UP I will create new Project with new Calendar Template:

image

Now I will add Task 1, Task 2, Task 3, and Task 4:

image

You can see that all Task are going to start at 4/13/2020. All of them are going to finish at the same date, except Task 2, since it has 2 days duration. Now I will assign Tim to all Tasks:

image

Since 1 day is 8 hours (from 09:00 AM to 05:00 PM, according to Calendar template), and Tim will work from 9:00 AM to 01:00 PM, eg. 4 hours per day, then:

  • Task 1 has 1 day Duration e.g. 8 hours. Tim will work two days, 4 hours per day, so Finish date is 4/14/2020
  • Task 2 has 2 day Duration e.g. 16 hours. Tim will work four days, 4 hours per day, so Finish date is 4/15/2020
  • Task 3 has 4 hours Duration. Tim will work one day, 4 hours per day, so Finish date is 4/13/2020
  • Task 4 has 5 hours Duration. Tim will work two days, 4 hours first day, and remaining one hour second day, so Finish date is 4/14/2020

Hope this helps.

Regards

Posted in MICROSOFT PROJECT, Microsoft Project for the Web, Project for the Web, Project for Web | Tagged | Leave a comment