Category Archives: MICROSOFT PROJECT

How to Change View in MS PROJECT 2019?

Hello, Today I will show you how to change View in MS PROJECT 2019! Let’s say that we have Project like this: As you can see, for this Project I have resources: and if I apply Cost Table on the … Continue reading

Posted in MICROSOFT PROJECT, MICROSOFT PROJECT 2019 | Tagged | Leave a comment

When to use Task Calendar in MS Project 2019

Hi, I have very good question form one Blog reader: “Hello Nenad. I found your website while trying to solve a very particular problem in MS Project. Unfortunately, I haven’t been able to find a solution and was hoping that … Continue reading

Posted in MICROSOFT PROJECT, MICROSOFT PROJECT 2019 | Tagged | Leave a comment

How to Delay Project in MS PROJECT 2019

Hi all, I have a question from one of my Blog readers: “The project I am involve in  is using only material resources and the unit rate for each resource did not change through time. Currently the project has more … Continue reading

Posted in MICROSOFT PROJECT, MICROSOFT PROJECT 2019, Micsrosoft Project 2016 | Tagged | Leave a comment

Task start date depending on predecessors competition–is that possible in MS PROJECT?

Hi, I’ve got interesting question from on of my blog readers and it is: “Let’s say that you have Task 1 and Task 2. Task 2 can start when 25% of Task 1 is completed, and Task 1 can continue … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2019 | Tagged , , | Leave a comment

Assign Resources to different time on the same Task in MS PROJECT 2016

Hi, one of my Blog readers has a questions: “One activity has 3 days Duration,  and we need to assign 2 resources. First resource will work all 3 days on it,  but second is only needed for 2nd day. How … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, PMI, PRoject Management | Tagged , | Leave a comment

Recording task progress ahead of schedule in MS PROJECT 2016!

Hi, my Blog reader has a problem with scheduling Task ahead of planned time! I will reproduce his scenario in MS PROJECT 2016!. First I’m going to create simple Project with two Tasks: Now I’m going to create two Resources … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Remaining work with Task in progress when new Resource is assigned is assigned in MS PROJECT 2016

Hi, in the first Post this year I will answer the question from one of my Blog readers: “How will MS Project calculate remaining work, when a resource is added to a task after baseline is assigned and work has … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment