% complete and Driving Tasks is Microsoft Project for the Web

Hi,

in one of my previous post I have explained Driving Tasks in Microsoft Project for the Web. Now I will show you how this effect Task which has % complete greater than zero.

First, I will crate new Project:

image

and in Timeline View:

image

Obviously Task 2 is Driving Task for Task 3, as it can be seen here:

image

Now, let’s say that Task 3 is 50% completed:

image

As you can see, Task 2 is no longer Driving Tasks for Task 3. Why is that? Because when Task has been started (as in my example, Task 3), it will not be moved even if, for example, Task 2 has extended Duration. Let me show you that. I will put 7 days in Duration field for Task 2, and I will get:

image

As you can see, Task 2 (and Task 1, too) has no impact on Start Date for Task 3, because it has been started (e.g. it has some % completeness). And therefore Driving Task for Task 3 doesn’t exist anymore.

Regards!

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, PMI, Project for the Web, Project for Web, PRoject Management and tagged . Bookmark the permalink.

Leave a Reply