Color indicators for Finish date in Microsoft Project for the Web

Hi,

Today I will show you color indicators for Finish date in Microsoft Project for the Web!

First I will create simple Project with five Tasks:

image

Current date is 05/10/2020, as you can see in Timeline View:

image

In a Grid View I will add two columns: Start and Finish, and I will get:

image

All Tasks have the same Start date, and it is Project Start date which is 05/04/2020.

  • Task 1 has 1 day Duration, and Finish date is 05/04/2020. Since today is 05/10/2020, this task is late, and Finish date is marked red
  • Task 2 has 5 days Duration, and Finish date is 05/08/2020. Since today is 05/10/2020, this task is late, and Finish date is marked red
  • Task 3 has 6 days Duration, and Finish date is 05/11/2020. Since today is 05/10/2020, and finish date is soon, this task is not late, but it should be completed soon, so it is marked yellow
  • Task 4 has 7 days Duration, and Finish date is 05/12/2020. Since today is 05/10/2020, and finish date is soon, this task is not late, but it should be completed soon, so it is marked yellow
  • Task 5 has 8 days Duration, and Finish date is 05/13/2020. Since today is 05/10/2020, and finish date is not so soon, this task is not late, and it is not marked in any color, so it means it’s status is good.

If current date is, for example 05/04/2020, then Task 1 will be marked yellow, but it’s finish date will not be shown as 05/04/2020, but it will be Today.

To conclude:

  • If finish date is not marked (e.g. it’s background is white) – the Task is in good shape
  • If finish date is marked yellow (e.g. it’s background is yellow) – the Task is still in good shape, but you should take care of it, because it can soon be in trouble, e.g. late Tasks
  • If finish date is marked red (e.g. it’s background is red) – the Task is not in good shape, and it means only two things: either you did not put % completed, or Effort completed (e.g. progress), or the Task is late.

Regards

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in Microsoft Project for the Web, Project for the Web and tagged . Bookmark the permalink.

Leave a comment