Changing Resource Calendars and Task Progress–Microsoft Project 2019

Hi,

today I will show you what happens if you change Resource Calendar AFTER Task is in progress with MS PROJECT 2019.

First I will create two simple Tasks:

image

and two Resources:

image

Now I will assign John to Task 1, and Mary to Task 2:

image

Finally, I will put 100% Completed for Task 1, and 50% Completed for Task 2:

image

Now, let’s say that I forgot that John and Mary are on education from Wednesday 21.01.2019 to Friday 25.01.2019, and they are not available for my Project:

image

When I do same thing for Mary, finally I will get:

image

As you can see, nothing has been changed for John, and Mary the Finish date is postponed to Tuesday 29.01.2019. Now, the question is: “Why the Task for John didn’t move as it did for Mary?”. And the answer is very simple: “Because it is marked as Done!” In MS PROJECT if Task is done (or just a part of it), you can change Calendar as you want but those dates (periods) in which Task is done will not be affected. If, for example, I put Education exception from 21.01.2019 to 24.01.2019 (the whole period), the result will be the same, e.g. since Task 1 is completed nothing will be changed, and Since Task 2 is only 50% complete (work is done at Monday and Tuesday), only remaining part will be affected. If you forgot to put Exception before Task is completed you should first mark this Task as 0% completed, then change the Calendar, and then mark it completed.

Regards.

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MS PROJECT 2019 and tagged . Bookmark the permalink.

Leave a comment