Category Archives: Project for Web

Non working hours bug in Microsoft Project for the Web

Hi Today I will show you a bug in Microsoft Project for the Web. Let’s say that we have two Resources: John and Ellen. At 01/15/2021 John is suppose to work from 01:00 PM to 05:00 PM, and Ellen is … Continue reading →

Posted in Microsoft Project for the Web, Project for the Web, Project for Web | Tagged | Leave a comment

Start and Finish time for Task in different Project Calendar using Microsoft Project for the Web!

Hi, today I will explain something that can seems as a bug, but it is not in Microsoft Project for the Web! It is a bit tricky, and I got an explanation directly from Microsoft. Let me show you! Firs … Continue reading →

Posted in Microsoft Project for the Web, PMI, Project for the Web, Project for Web, PRoject Management | Tagged | Leave a comment

Time off for specific Resources in Microsoft Project for the Web

Hi, I’m going to show you how to setup, for example, Vacation for specific Resource, using Microsoft Project for the Web. Let’s say that Ellen will take day off at 01/01/2021, but everyone else will work at that Day. To … Continue reading →

Posted in Microsoft Project for the Web, PMI, Project for the Web, Project for Web, PRoject Management | Tagged | Leave a comment

Effort calculation with different Calendars in Microsoft Project for the Web!

Hi, today I will show you how Microsoft Project for the Web calculate effort when Resources have different Calendars. First of all let’s see Calendars for two Resources: Tim and Ellen: and: Let’s see Ellen’s Calendar: and finally: Believe me, … Continue reading →

Posted in Microsoft Project for the Web, Project for the Web, Project for Web, PRoject Management | Tagged | Leave a comment

Go to date function and dates in Timeline–Project for the Web!

Hello, today I will show you the Go to date function and dates in Timeline using Project for the Web. First, I will create a simple project: I will switch to Timeline view: Now, let’s say that I want to … Continue reading →

Posted in PMI, Project for the Web, Project for Web, PRoject Management | Tagged | Leave a comment

How to export Project for the Web to Excel

Hi, the new feature for Microsoft Project for the Web is Export to Excel. Let me show you how is this possible. First I will create a simple Project: Tasks are in separate Buckets: Now, I will export this Project … Continue reading →

Posted in Microsoft Project for the Web, PMI, Project for the Web, Project for Web | Tagged | Leave a comment

How to create Project for the Web in Teams

Hi, today I will show you how can a Project for the Web be created for Team. First of all I will open my Team in Microsoft Teams: ¸ and then I will look for the Project: Next step is: … Continue reading →

Posted in Microsoft Project for the Web, Project for the Web, Project for Web, PRoject Management | Tagged | Leave a comment

Duration vs. effort in Microsoft Project for the Web

Hi, today I will show you connection between Duration and Effort (known as work). I will create simple Project As you can see, I have two Tasks. Task 1 has no resource assigned, Task 2 has John as resource! Now, … Continue reading →

Posted in Microsoft Project for the Web, PMI, Project for the Web, Project for Web, PRoject Management | Tagged | Leave a comment

Task Types in Microsoft Project for the Web

Hi, Today I will show you what kind of Task Types are available in Microsoft Project for the Web. As we know, in Project desktop version Fixed Units, Fixed Duration, and Fixed Work, are available. In Microsoft Project for the … Continue reading →

Posted in Microsoft Project for the Web, Project for the Web, Project for Web | Tagged | Leave a comment

How to create Project from PowerApps

Hi, today I will show you how to create Project form PowerApps. First I will login into Office365: and then: and finally: this is what I have: Now I will create a brand new Project: When I choose Tasks Tab … Continue reading →

Posted in PMI, Project for the Web, Project for Web | Tagged | Leave a comment