Hi,
as we know, when we use Microsoft Project Desktop, or Project online, we have various ways to see Tasks on Critical path. In Microsoft Project for the Web, for now, there is not such option available. BUT! If you use Project Accelerator, there is a way to get them.
First of all I will create a Project using Microsoft Project for the Web:
Let’s see the Timeline View:

Remember, this is a simple Project, and I can see Critical path, but on more complex Project I will not be able to see it. So, I will export this Project using Project Accelerator:

and I will get:

Finally I will get:

As you can see, there is a Column called Critical! Be aware that here are all Tasks from just My Project, but if I have more that one Projects, all Tasks from all Projects will be shown here. So, if I want to see Tasks from Critical path on particular Project, first I have to filter Project (Column C), and then Critical Tasks (Column G).
It is bit complicated, but for now this is the way to get Critical Tasks.
Ladies and gentleman, I am writing Blog Post weekly since 2012. I will continue with my community contribution, but from now on I will start to record Videos, e.g. I will start with Vlogs. Each and every time when I will publish new Video on my YouTube channel, you will be noticed here, with link provided.
I hope that you will enjoy them as you enjoyed my Blog post, and that it will be helpful.
Thank you very much for reading.
Best regards!
About Nenad Trajkovski
Location: Zagreb, Croatia
Occupation: Project Manager
Interests: Project Management and MS PROJECT
He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!