Goodbye and Hello

Hi,

After 10 years of blogging, here is my first vlog! From now on, you can expect only videos about Microsoft Project!

The channel is: Managing Projects with Microsoft tools: https://www.youtube.com/channel/UCEXjYVWzddohtykIqRvPIgQ

My first video is here: Introduction to Microsoft Project for the web – YouTube

Thank you very much for your comments, suggestions and reading during all those years. I hope that you will enjoy Videos as you enjoyed Blogs. I will keep posting my Videos on regular basics – once per week.

Love you all,

Nenad

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft Project for the Web, PMI, Power Apps, Power Platform, PRoject Management and tagged . Bookmark the permalink.

Leave a comment