-
Recent Posts
Archives
Categories
Category Archives: Microsoft Project for the Web
Start and Finish time for Task in different Project Calendar using Microsoft Project for the Web!
Hi, today I will explain something that can seems as a bug, but it is not in Microsoft Project for the Web! It is a bit tricky, and I got an explanation directly from Microsoft. Let me show you! Firs … Continue reading
Time off for specific Resources in Microsoft Project for the Web
Hi, I’m going to show you how to setup, for example, Vacation for specific Resource, using Microsoft Project for the Web. Let’s say that Ellen will take day off at 01/01/2021, but everyone else will work at that Day. To … Continue reading
Effort calculation with different Calendars in Microsoft Project for the Web!
Hi, today I will show you how Microsoft Project for the Web calculate effort when Resources have different Calendars. First of all let’s see Calendars for two Resources: Tim and Ellen: and: Let’s see Ellen’s Calendar: and finally: Believe me, … Continue reading
How to export Project for the Web to Excel
Hi, the new feature for Microsoft Project for the Web is Export to Excel. Let me show you how is this possible. First I will create a simple Project: Tasks are in separate Buckets: Now, I will export this Project … Continue reading
How to create Project for the Web in Teams
Hi, today I will show you how can a Project for the Web be created for Team. First of all I will open my Team in Microsoft Teams: ¸ and then I will look for the Project: Next step is: … Continue reading
Duration vs. effort in Microsoft Project for the Web
Hi, today I will show you connection between Duration and Effort (known as work). I will create simple Project As you can see, I have two Tasks. Task 1 has no resource assigned, Task 2 has John as resource! Now, … Continue reading
Task Types in Microsoft Project for the Web
Hi, Today I will show you what kind of Task Types are available in Microsoft Project for the Web. As we know, in Project desktop version Fixed Units, Fixed Duration, and Fixed Work, are available. In Microsoft Project for the … Continue reading
% Complete for Project as a whole and Summary Task in Microsoft Project for the Web
Hi, today I will show you how % Complete is calculate on Summary Task level, and on Project Level as well, using Microsoft Project for the Web! First, I will create one simple Project: Firs three Tasks are connected, and … Continue reading
Dependencies on Timeline View with Microsoft Project for the Web!
Hi, today I will show you how beautiful is Timeline View in Microsoft Project for the Web. We all know how difficult is to manage Projects with many Tasks. It is hard to see for a Task all Predecessors, and … Continue reading
How to set different Work days during time period with Microsoft Project for the Web
Hi, Today I will show you how to set different Work days during time period with Microsoft Project for the Web! Here is Scenario. Until 10/01/2020 (October the 1st), work days are going to be from Monday to Friday. From … Continue reading