Task Types and how they affect the Schedule–Part 2

 

Hi,

let’s go. First we will do a Setup!

I will add two Tasks to my Project:

image

I will make Paint the wall effort driven:

image

Now I will add two Resource to the Project: John and Mary!

image

I will assign John to the Read the article Task and Mary to the Paint the wall Task.

image

Finally I will set the Views. First Task Usage:

image

and now:

image

When you click on the lower part of the screen (in the Task Form) you should go to the Format Tab and do:

image

Everything is ready!

I will click on the Read the Article Task and I will get:

image

As you can this Task has: Duration = 2 days, it is non effort driven, fixed units it has 100% units, and Work = 16 hours. Work = Duration * Units –> Work = 2 days (8 hours per day) * 100% = 16 hours * 100% = 16 hours.

I will change Units from 100% to 150%:

image

and I will get:

image

Work is same = 16 hours! Because John can work with 150% capacity, he will work 8 * 150% = 12 hours at first day, and remaining 4 hours at second day, to fulfill 16 hours! But why is Duration=1,33 days? It seem it should be 1,5 day (because John will work only 4 hours at second day, instead of 8)! Well here is the explanation! Because I put 150% in Unit, MS PROJECT assumes that John has to work 12 hours / day (150% * 8 hours= 12 hours). And the Duration is calculated: 12 hours on first day = 1 day! 4 hours on second day (4/12)= 0,33, and total is = 1 + 0,33 = 1,33

OK. Now I will go back to initially Setup:

image

and I will change Work to 32 hours, click on OK button, and I will get:

image

Work is 32 hours! Because Task is Fixed Units, John will work with 100% capacity. The Magic Formula is Work = Duration * Units, and that means 32 = Duration * 100%. Because 1 day has 8 working hours It will be 32/8 = 4 days in the Duration field.

 

Finally I will (from initial setup) change the Duration from 2 to 3 days, click on the OK button, and I will get:

image

Duration is 3 days! Because Task is Fixed Units, John will work with 100% capacity. The Magic Formula is Work = Duration * Units, and that means Work = 3 days (8 hours per day) * 100%. = 24 hours.

In my next post I will continue with Fixed work and Fixed duration Task types.

Until then,

Best Regards!

Advertisement

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s