Projects related to Calendar templates–Project for the Web

Hello,

Let’s suppose that I have Projects related to two Calendar Templates:

  • Template from 09:00 AM to 05:00 PM GMT+1
  • Template from 09:00 AM to 05:00 PM GMT-8

I have two Projects related to Template from 09:00 AM to 05:00 PM GMT+1:

image

and:

image

I have another two Project related to Template from 09:00 AM to 05:00 PM GMT-8:

image

and:

image

OK. I want to know which Projects are related to each Template. To do that I should follow next steps:

image

and:

image

Now, I will choose:

image

and then:

image

Finally, I will get:

image

So here are all Project related to specific Template, which I choose.

If I choose Template from 09:00 AM to 05:00 PM GMT-8, I will get:

image

To conclude, when I have Projects in different Time zones, this is the way to see all Projects which belongs to specific Time zone.

Hope this helps.

Best Regards!

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in Microsoft Project for the Web, Project for the Web and tagged . Bookmark the permalink.

Leave a Reply