Constraints and deadline in MS PROJECT

In this post I will write about constraints

There are three types of constraints:

  1. Flexible constraints. This is a default type of constraint in MS PROJECT. It means that a task can start As Soon As Possible
  2. Semi-flexible constraints. A task must begin or end no later than the defined date
  3. Inflexible constraint. A task must begin or end on a certain date.

Flexible
As Soon As Possible
Project will schedule a task to  occur as soon as it can occur.  This is the default constraint type applied to all new tasks when scheduling from the project start date. There is no constraint date for an ASAP constraint.

As Late As Possible
Project will schedule a task tooccur as late as it can occur. This  is the default constraint type applied to all new tasks when scheduling from the project finish date. There is no constraint date for an ALAP constraint.

Semi-flexible
Start No Earlier Than
Project will schedule a task to start on or after the constraint date that you specify. Use this  constraint type to ensure that a task will not start before a specific date.

Start No Later Than
Project will schedule a task to start on or before the constraint date that you specify. Use this constraint type to ensure that a task will not start after a specificdate.

Finish No Earlier Than
Project will schedule a task to finish on or after the constraint date that you specify. Use this constraint type to ensure that a task will not finish before a  specific date.

Finish No Later Than
Project will schedule a task to finish on or before the constraint date that you specify. Use this constraint type to ensure that a  task will not finish after a specific date.

Inflexible
Must Start On
Project will schedule a task to start on the constraint date that you specify. Use this constraint type to ensure that a task will start on an exact date.

Must Finish On
Project will schedule a task to finish on the constraint date that you specify. Use this constraint type to ensure that a task will finish on an exact date.

Which type to choose? Well, the best approach is to use Flexible constraint.

This type of constraint lets MS PROJECT to schedule task with only one limitation and that is, predecessor and successor relationship. In previous picture you can see that TASK 2 will start immediately after TASK 1 ends.

If you use semi-flexible constraint like, for example, Start no Earlier Than, task will start no earlier than date you have entered in the Constraint date field, but it can start later than this date if its predecessor ends later than given date.


If you use inflexible constraint like, for example, Must start on, task will start on specific date (no prior and no later than given date). In my next example I have TASK 1 which will start on 31.03.2011 and finish on 01.04.2011 (2 day duration), and its successor TASK 2
which will start on 04.04.2011 and finish on 06.04.2011 (3 day duration). Now I
will put the inflexible constraint Must Start On and the constraint date will be 01.04.2011 (see the picture below):

When I click on OK button I get this:

This is a warning screen. It asks you: “What do you want to do?”
If you choose: “Cancel. No constraint will be set on ‘TASK 2’” you are actually cancelling the whole thing
If you choose: “Continue, but avoid the conflict using a Start No Earlier Than constraint instead” the constraint will be changed from Inflexible->Must Start On to Semi-flexible-Start No Earlier than
If you choose: “Continue. A Must Star On constraint will be set.” You will get (from my example) this:


If you choose: “Cancel. Avoid the scheduling conflict” you are actually cancelling the whole thing
If you choose: “Continue. Allow the scheduling conflict” you will get negative slack (see
the picture below):

For a Task you can enter duration, start or finish date:


If you enter a Duration (and only duration) you are setting flexible constraint->As soon as possible (when scheduling from the project start date). If you enter a Start date you are applying a Start No Earlier constraint. If you enter a Finish date you are applying a Finish No Earlier constraint.
If you know that your task has a deadline one common mistake is to put inflexible constraint -> must finish on. Suppose that you have a task with 1 day duration and the deadline is 01.04.2011. If you put Must finish on constraint with 01.04.2011 you are increasing the risk for this task. Why? Because you are telling MS PROJECT that this task MUST finish on that date and NOT BEFORE.  What if your required resource is sick?Better approach is to let MS PROJECT to handle start date with As Soon As possible constraint and put the deadline information about the task.

Here is the example: We have the TASK with 3 day duration:

We have the deadline for this task and it is 05.04.2011.
We will put it here:


And we will get the Deadline indicator in our Gantt diagram:

 

See you!

Unknown's avatar

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management. Bookmark the permalink.

22 Responses to Constraints and deadline in MS PROJECT

  1. Sarah Good's avatar Sarah Good says:

    Thank you for this post. I am having an issue where MS Project will automatically set constraints to my tasks. Typically is sets is as “start no earlier than,” and it gives me a very hard time in changing this. Whether I’m trying to adjust the date that is set, or simply remove the constraint all together, it usually makes me do it several times before it allows the change to take place. Do you have any advice on how I can avoid this issue? Thank you 🙂

    • Nenad Trajkovski's avatar Nenad Trajkovski says:

      Plaesa sent me example (mpp file) to neneadtrajk@gmail.com. It will make a Task to Start noi earlier automatically if you enter start date by yourself!

      • Carol Brits's avatar Carol Brits says:

        Hi Nenad
        I have the exact same issue as Sarah explained on this post. My tasks are all set to automatically scheduled. I update actuals weekly and once completed I update the project and select ‘reschedule uncompleted work to start after xxxxx’ . MS project then automatically sets a ‘start no earlier’ constraint with date date(xxxxx) on some of my tasks. I then manually need to remove them the next time i want to update the schedule. Any ideas what is driving this behaviour would be appreciated.
        Thanks
        Carol

      • Nenad Trajkovski's avatar Nenad Trajkovski says:

        Read my Blog post wrote at Feb 4th

  2. Pingback: Start and Finish Date with Auto Scheduled Task | Nenad Trajkovski

  3. Richard's avatar Richard says:

    Please can you help me. I would like to know how I can ask MS project to set one task ALAP without causing successors to move ALAP as well. In other words, I like to keep all tasks as MS default setting (ASAP) except one task to be set as ALAP.

    Your response will greatly be appreciated.

  4. asbestos abatement removal's avatar asbestos abatement removal says:

    Who is the individual who published this posting? What is the easiest way to get in touch?
    I prefer by phone, but e-mail is okay too.

  5. Susanna's avatar Susanna says:

    What is the preferred way to communicate with the individual that
    created this content? Can you please provide either a phone
    number or private e-mail address? Thank you so much.

  6. mold removal toronto's avatar mold removal toronto says:

    Is there a commentary form where we can get in touch
    with the creator of this post? What’s the most effective way to reach out?

  7. Mohamed Fathy's avatar Mohamed Fathy says:

    Really it is great blog for both Ms project 2010 and Project Server 2010

  8. mike's avatar mike says:

    Thanks for a great Blog…just a quick queston…Is it good practise to put a “Finish No Later Than
    ” constraint as well as a setting the task with deadline with the same date

  9. mike's avatar mike says:

    Thanks for a great Blog…just a quick queston…Is it good practise to put a “Finish No Later Than
    ” constraint as well as a setting the task with deadline with the same date

    • Nenad Trajkovski's avatar Nenad Trajkovski says:

      Well, deadline gives you more flexibility, but if you want to make a semi flexibile constarint use FINISH NO LATER. In that case you don’t need deadline!

  10. Abraham's avatar Abraham says:

    I am motivated by your achievements Nenad T, I can now start dreaming.

  11. Nenad Trajkovski's avatar Nenad Trajkovski says:

    I’m glad that You like it 🙂

  12. How much house can I afford's avatar How much house can I afford says:

    are you on linkedin?

Leave a reply to Mohamed Fathy Cancel reply