Category Archives: MS PROJECT 2010

Effort without specific Tasks in Projects using Microsoft Project 2016!

Hi, often I have a question like this: “How to assign Work to someone when that work is not to be linked with any specific Task?”. I will show you how with MS PROJECT 2016! But first I have to … Continue reading

Posted in Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , , | Leave a comment

Project Summary Task and Calendars in Microsoft Project 2016

  Hi, I have interesting question from my Blog reader: “How does one change the calendar for the Project Summary Task? The schedule is developed and has a calendar, other than the standard calendar, associated with all the tasks, but … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Update the task as 100% without changing work hours automatically in MS PROJECT 2016 – is it possible?

Hi, I’ve got very good question from one of my Blog Readers: “How can I do to update the task as 100% but without changing work hours automatically? Because I want to know that my team is more efficient than … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, MS PROJECT 2016 | Tagged , , | Leave a comment

How to disconnect relation between %Complete and %Work complete in MS PROJECT 2016?

  Hi, I have a question from one of my blog readers: “Hi,I just came across your resource tool and am hoping to find some help. I am having trouble disconnecting % Work Complete (Actual work done) from % Complete … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , | 3 Comments

%Complete, %Work Complete, and Project without Resources with MS PROJECT 2016!

Hi, I’ve got a question from one of my Blog Readers: “Please clarify the following: I have created a Sample project in MS Project 2013, with tasks and assigned duration  with required predecessors.I have base lined the plan and started … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , , | Leave a comment

Actual Duration, Actual work and Fixed work Tasks in MS PROJECT 2016

Hi, here is one problem that my Blog Reader has (I will go step by step, and I will use MS PROJECT 2016) “When multiple resources are assigned to the task, for a given Total Work we can  calculates the   … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , | 1 Comment

Effect of initial resource assignment on calculation of Individual resource’s work in MS PROJECT 2016

Hi, I’ve got very good question form one of my Blog readers: “The effect  of initial resource assignment on  calculation  of  Individual resource’s work. Suppose we want have two resources R1 (100%) and R2(50%) to work on a 20h fixed … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | 4 Comments