Tag Archives: Micorosft Project 2016 – Tasks

Multiple assignments on the same Task in MS PROJECT 2016

  Hi, my Blog Reader has a very interesting question: “Hi Nenad I have a problem, and I hope you can help me, I’m a follower of your blog. I have some task on project and resources, but I want … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Task Summary Name–new field in MS PROJECT 2016

Hi, There is one new Task related field in MS PROJECT 2016: Task Summary Name. It is very useful. Usually Summary Tasks have a lot of subtasks, and when you group them, filter them or just look at them, you … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 5 Comments

Placeholder field in MS PROJECT 2016

Hi, in MS PROJECT 2016, there is on, not so often used, field – Placeholder. Let me create new Project with three Tasks: As you can see, Task 1 and Task 2 are Manually scheduled, and Task 3 is Auto … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Move vs Update Tasks in MS PROJECT 2016

Hi, in my last post I wrote about differences between Move and Update options in MS PROJECT 2016 on the Project Level, Now it is time to explain those two different options on the Task level. First, I will create … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Fixed duration Tasks and over allocation resolution in MS PROJECT 2016

Hi, I have interesting question form one of my Blog Readers: “I have below query in Fixed Duration Task.Step1: created a task “paint the wall” with duration as 10 days (work starts by a Monday). Task is fixed durationStep2: created … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | 2 Comments

Replacing Resources on partial done Tasks–Microsoft Project 2016

Hi, I have a question from my Blog reader: “Hi Nenad and thank you very much for your blog. I have a question for you. Suppose you have a 10d task with a generic resource assigned to it ( total … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , , , | 1 Comment

Some leveling options in Microsoft Project 2016

Hi, my Blog reader has a question: “Would you please give an example with “Leveling Can Adjust Individual Assignments on a Task” and an other example with “Level Resources with the Proposed Booking Type” in MS Project 2016 resource leveling … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment