Duration and % completed–relation between them in MS PROJECT 2016

Hi, I noticed that lot of MS Project users have a problem with Duration and work which was already completed. Let me give you an example in MS PROJECT 2016. Let’s say that we have a one Task Project, with … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Project management Task and Administrative work in MS PROJECT 2016

Hi, my blog reader has a question about Project management Task, and administrative work, and how to handle it in MS PROJECT 2016? Here is Scenario. This is Project Schedule: First of all, I will advice not to use Project … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | 1 Comment

Additional Resources assigning to the Task which have work in progress in MS PROJECT 2016

Hi, Today I’m going to explain what happens if I assign additional resource in Task which has a progress with MS PROJECT 2016. First, I’m going to create brand new Project: I have two resources available: I will assign John … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2016, PMI | Tagged , , | Leave a comment

Inactive Tasks and Actuals in MS PROJECT 2016

Hi, I saw very interesting discussion in LinkedIn, about making Task Inactive if it has actuals. First let me show the “issue”. I will create brand new Project in MS PROJECT 2016: and I will create John as Resource with … Continue reading

Posted in MS PROJECT 2016 | Tagged , , , | Leave a comment

Scheduled Start and Scheduled Finish fields in MS PROJECT 2016

Hi, today I will explain two fields, not so often used in MS PROJECT 2016: Scheduled Start and Scheduled Finish. First I will create one simple Project with three Tasks, connected like this: As you can see Scheduled Start is … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

New way of choosing Predecessors and Successors in MS PROJECT 2016

Hi, If you work with the latest version of MS PROJECT 2016, and you have update it regular you will notice one great improvement in Predecessor field. Let me show you that. First I will create brand new Project with … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 1 Comment

Multiple assignments on the same Task in MS PROJECT 2016

  Hi, my Blog Reader has a very interesting question: “Hi Nenad I have a problem, and I hope you can help me, I’m a follower of your blog. I have some task on project and resources, but I want … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Task Summary Name–new field in MS PROJECT 2016

Hi, There is one new Task related field in MS PROJECT 2016: Task Summary Name. It is very useful. Usually Summary Tasks have a lot of subtasks, and when you group them, filter them or just look at them, you … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 7 Comments

Placeholder field in MS PROJECT 2016

Hi, in MS PROJECT 2016, there is on, not so often used, field – Placeholder. Let me create new Project with three Tasks: As you can see, Task 1 and Task 2 are Manually scheduled, and Task 3 is Auto … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Move vs Update Tasks in MS PROJECT 2016

Hi, in my last post I wrote about differences between Move and Update options in MS PROJECT 2016 on the Project Level, Now it is time to explain those two different options on the Task level. First, I will create … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment