Tag Archives: Micorosft Project 2016

Resource replacement whit already assigned resource on Task in Progress–MS PROJECT!

Hi, I’ve got a question from one of my blog readers: “Let’s suppose that I have a task “Task” with fixed work task type. Duration is 10 days. I assign 2 resource who work for 8hr per day. Total work … Continue reading

Posted in Micsrosoft Project 2016, MS PROJECT 2016, PMI | Tagged , , | 1 Comment

Fixed cost for resource over the time period in MS PROJECT 2016

Hi, I’ve got a question from one of my Blog readers: “Mr. Nenad, I have a question please:Let’s suppose that I have a human work resource assigned to different tasks within the project. It receive each month a fixed salary … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Resource detail form in MS PROJECT 2016

Hi, as I wrote many times there is a very useful Task form in MS PROJECT 2016! Here is one simple project: With the Task form we have full control over the Task, like this: In Task form we can … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

Duration and % completed–relation between them in MS PROJECT 2016

Hi, I noticed that lot of MS Project users have a problem with Duration and work which was already completed. Let me give you an example in MS PROJECT 2016. Let’s say that we have a one Task Project, with … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Recording task progress ahead of schedule in MS PROJECT 2016

Hi, today I am going to clarify one important thing which bothers a lot of  of my Blog readers. I will go step by step through example and explain them. First I’m going to build simple Project: Now I will … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , | 1 Comment

Calculate Variance in Working Days after setting another baseline in MS PROJECT 2016

Hi, I’ve got a question which is: “How do you calculate the working days in formulas when the baseline is not Baseline 0, and you need to see variance of that Baseline?” It’s easy and I’ll show you how with … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , | 1 Comment

Material resources over different time than workload in MS PROJECT 2016

Hi, I have interesting question from one of my Blog readers:”I am working with Engineering services provider. I have created my resource pool sheet. I have assigned my resources (Employees/Engineers) on different projects. These engineers use different tools (licenses etc.) … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment