Fixed cost for resource over the time period in MS PROJECT 2016
Hi, I’ve got a question from one of my Blog readers: “Mr. Nenad, I have a question please:Let’s suppose that I have a human work resource assigned to different tasks within the project. It receive each month a fixed salary … Continue reading
Costs for no work done in MS PROJECT 2016
Hi, again my Blog reader has a problem, which is: “I have a question. Let’s say I have 4 hours of delay against a project as “ALL RESOURCES” had to wait for a crane to arrive before work could commence. … Continue reading
Costs in Task Form combined with Gantt Chart View in MS PROJECT 2016
Hi, Task Form is very useful thing in MS PROJECT 2016, and it can be use in various ways. Today I’ll show how to see Costs for Task per Resource. First I will create simple new Project: Now I Will … Continue reading
Overtime work at specific day–is it possible in MS PROJECT 2016?
Hi, In this post, I will show you answer to one of my blog readers. He asked me is it possible to put Overtime Work at specific day in MS PROJECT 2016? Let’ say that we have a simple Project, … Continue reading
Multiple Costs types for Resource in a same Task
Hi, I have very interesting question from on of my Blog readers: “I have a problem with MS Project: I don’t know how to manage 2 type of cost for 1 person, I mean, I have 1 employee with 100USD … Continue reading
Resource rates and Billing rates in MS PROJECT 2016
Hi! I always get a question like this: “I need to charge an hourly rate per project. My hourly rate is $100.00 per hour. I have an employee work for me. Their rate is $20.00 per hour. I need to … Continue reading
New Tasks and saved Baseline in MS PRIOJECT 2016
Hi, I have a reader who is novice in MS PROJECT 2016, and he has a problem; “Hi, I hope you are in good health. I have some quires about cost tracking in MS Project. I had previously saved … Continue reading
How to change rates and costs without affecting past Tasks in MS PROJECT 2016?
Hi, I’ve got a question from one of my Blog Readers: “Hi!I am wondering how you would manage a rate increase in MS Project halfway through the project that is not retroactive. If I change the $/hr for a resource, … Continue reading