Tag Archives: Micorosft Project 2016 – Resources
Resource replacement whit already assigned resource on Task in Progress–MS PROJECT!
Hi, I’ve got a question from one of my blog readers: “Let’s suppose that I have a task “Task” with fixed work task type. Duration is 10 days. I assign 2 resource who work for 8hr per day. Total work … Continue reading
Fixed cost for resource over the time period in MS PROJECT 2016
Hi, I’ve got a question from one of my Blog readers: “Mr. Nenad, I have a question please:Let’s suppose that I have a human work resource assigned to different tasks within the project. It receive each month a fixed salary … Continue reading
Resource detail form in MS PROJECT 2016
Hi, as I wrote many times there is a very useful Task form in MS PROJECT 2016! Here is one simple project: With the Task form we have full control over the Task, like this: In Task form we can … Continue reading
Material resources over different time than workload in MS PROJECT 2016
Hi, I have interesting question from one of my Blog readers:”I am working with Engineering services provider. I have created my resource pool sheet. I have assigned my resources (Employees/Engineers) on different projects. These engineers use different tools (licenses etc.) … Continue reading
Fixed Duration Tasks and Resource availability in MS PROJECT 2016
Hi, today I will show you what happens wen you have Fixed Duration Tasks with Resources assigned to them, and those resource are unavailable at the specific time. I will use MS PROJECT 2016 First I will create simple Project … Continue reading
How to avoid unnecessary Resources in MS PROJECT 2016
Hi, as you may already know, you can put Resources in MS PROJECT in many different ways. Sometimes this is good, but sometimes it can be very annoying. I will show you one example with MS PROJECT 2016! First I’m … Continue reading
“Real” daily work on Tasks in MS PROJECT 2016!
Hello, today I’m going to deal whit one significant question which basically has many answers, or none. How many hours to assign to Resource per day? Let me show you one very, very simple example. Let’s say that we have … Continue reading
Project management Task and Administrative work in MS PROJECT 2016
Hi, my blog reader has a question about Project management Task, and administrative work, and how to handle it in MS PROJECT 2016? Here is Scenario. This is Project Schedule: First of all, I will advice not to use Project … Continue reading
How to build Project Schedule with Task form using MS Project 2016
Hi, Today I will show you how to build schedule using Task form in MS PROJECT 2016. First I will create a simple Project: I will create two Resources: Now, it is time to create Schedule! Which Task has which … Continue reading
Remaining work with Task in progress when new Resource is assigned is assigned in MS PROJECT 2016
Hi, in the first Post this year I will answer the question from one of my Blog readers: “How will MS Project calculate remaining work, when a resource is added to a task after baseline is assigned and work has … Continue reading