Over allocation not shown in MS PROJECT 2016 with Windows 10–Bug or not?

Hi, My blog reader has a problem. He explained it step by step, and I will answer at it in the same way. Project in certain instances doesn’t flag  over allocated resources.For example, I created a resource John and assigned … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 1 Comment

Multiple assignments on the same Task in MS PROJECT 2016

  Hi, my Blog Reader has a very interesting question: “Hi Nenad I have a problem, and I hope you can help me, I’m a follower of your blog. I have some task on project and resources, but I want … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Resource with assignment 0%–what is it?

Hi, You can find a lot of examples when you can see that it is possible to assign Resource to Tasks with 0% Units. In this post I will show you how can you do it, and what would happen … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

How to automatically change Material relative to Scope change in MS PROJECT 2016

Hi, I’ve got very good question from one of my Blog readers: “Hi,I am a novice. Tried to find some solution to a certain scenario in your blogs but browsing through some dozen articles, I thought it better to ask … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Assignment Delay field in MS PROJECT 2016

Hi, in Microsoft Project 2016 there is one very useful field called: Assignment Delay. Let me show you how useful is it, and how can you use it. First, as I always do, I will create simple Project: I will … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Units field in Resource assignment – MS PROJECT 2016

Hi, I’ve got a question from one of my Blog readers: “Max units field in Assign Resources are always in %? I want to use QTY instead of %, like we have 10 cranes available, and how many cranes are … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

How to make week shifts in MS PROJECT 2016?

Hi, Today, I will explain next Scenario in MS PROJECT 2016: Suppose that you have a project team who will work 5 days a week (Monday to Friday), but every third week the whole team will be off. This is … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, PMI, PRoject Management | Tagged , , , , | Leave a comment