Tag Archives: Micorosft Project 2016 – Resources

Units field in Resource assignment – MS PROJECT 2016

Hi, I’ve got a question from one of my Blog readers: “Max units field in Assign Resources are always in %? I want to use QTY instead of %, like we have 10 cranes available, and how many cranes are … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

How to make week shifts in MS PROJECT 2016?

Hi, Today, I will explain next Scenario in MS PROJECT 2016: Suppose that you have a project team who will work 5 days a week (Monday to Friday), but every third week the whole team will be off. This is … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, PMI, PRoject Management | Tagged , , , , | Leave a comment

When to use Resource Calendars in MS PROJECT 2016

Hi, after my Post “Different weekends for Resources in MS PROJECT 2016”, there was a lot of discussion, that a problem can be solved with Resource Calendars, and that be will be the best way. Yes, it can be done … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 1 Comment

% Work Completed without Resources assigned to Tasks

  Hi, I wrote several Posts about % Work completed field, and how does it change when assigned Resources to the Task. As you know, Work is 0 hours until you assign Resource to the Task. But, is it possible … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project Server 2010, MS PROJECT 2016 | Tagged , , | Leave a comment

Replacing Resources on partial done Tasks–Microsoft Project 2016

Hi, I have a question from my Blog reader: “Hi Nenad and thank you very much for your blog. I have a question for you. Suppose you have a 10d task with a generic resource assigned to it ( total … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , , , | 1 Comment

Some leveling options in Microsoft Project 2016

Hi, my Blog reader has a question: “Would you please give an example with “Leveling Can Adjust Individual Assignments on a Task” and an other example with “Level Resources with the Proposed Booking Type” in MS Project 2016 resource leveling … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

%Complete vs. %Work Complete in MS PROJECT 2016!–when to use what?

  Hi, very often I have questions like this one: Dear Nenad, I am going to develop a scheduled for a petrochemical plant shutdown project. My question is: “What percent complete should i use (% Complete or Work % Complete) … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | 2 Comments