How to avoid unnecessary Resources in MS PROJECT 2016

Hi, as you may already know, you can put Resources in MS PROJECT in many different ways. Sometimes this is good, but sometimes it can be very annoying. I will show you one example with MS PROJECT 2016! First I’m … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

“Real” daily work on Tasks in MS PROJECT 2016!

Hello, today I’m going to deal whit one significant question which basically has many answers, or none. How many hours to assign to Resource per day? Let me show you one very, very simple example. Let’s say that we have … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Project management Task and Administrative work in MS PROJECT 2016

Hi, my blog reader has a question about Project management Task, and administrative work, and how to handle it in MS PROJECT 2016? Here is Scenario. This is Project Schedule: First of all, I will advice not to use Project … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

How to build Project Schedule with Task form using MS Project 2016

Hi, Today I will show you how to build schedule using Task form in MS PROJECT 2016. First I will create a simple Project: I will create two Resources: Now, it is time to create Schedule! Which Task has which … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , , , , | Leave a comment

Remaining work with Task in progress when new Resource is assigned is assigned in MS PROJECT 2016

Hi, in the first Post this year I will answer the question from one of my Blog readers: “How will MS Project calculate remaining work, when a resource is added to a task after baseline is assigned and work has … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Task Actual Start and Finish date when Resources are unavailable in MS PROJECT 2016

Hi, in this last post for year 2018. I will show you how Actual Start and Finish date are affected with Resource Calendar in MS PROJECT 2016. First I will crate Simple Project with one Task: I will create Two … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016 | Tagged , , | Leave a comment

How to hold Total Hours of work per Task when Actual Work is less then estimated hours in MS PROJECT 2016?

Hi, Today I’m going to explain how to solve a problem which one of my Blog Readers have in MS PROJECT 2016. Let us say that we have a Project with Task which is 6 weeks long. For this Task … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016 | Tagged , , | Leave a comment