How to avoid unnecessary Resources in MS PROJECT 2016

Hi,

as you may already know, you can put Resources in MS PROJECT in many different ways. Sometimes this is good, but sometimes it can be very annoying. I will show you one example with MS PROJECT 2016!

First I’m going to create new Project:

image

and some Resources:

image

Now I will assign some of them to the Task 1 through Gantt chart View:

image

and I will get:

image

Now let’s say that I want to assign Johnny Cash to Task 2, but I accidentally type Jonhhy and hit the Enter key:

image

As you can see MS PROJECT let me do that, and if I now look at the Resource Usage View I will find new Resource in it, even if I didn’t want it because this was obviously a mistake:

SNAGHTML3e5eb39

So, to correct this error I should erase Jonhhy form this sheet. If I do  not want MS PROJECT let me to enter Resource which is not already in Resource sheet, like in example above, I should disable it like this:

image

and:

image

and then:

image

Now, for example if I want to add Mary to Task 3, I will get:

image

when I hit Enter key:

image

Now I can choose if I want or not add Mary to my Resources, because she doesn’t exist in Resource Pool.

also be aware that this will apply only for the current Project on which I’m working at. If I want this option to be applied on al new Project I should choose:

image

Hope this helps.

Regards!

Advertisement

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MS PROJECT 2016, PMI, PRoject Management and tagged , , . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s