Duration and % completed–relation between them in MS PROJECT 2016

Hi, I noticed that lot of MS Project users have a problem with Duration and work which was already completed. Let me give you an example in MS PROJECT 2016. Let’s say that we have a one Task Project, with … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Total hours limit with multiple Projects using MS PROJECT

Hi, I have a question from one of my Blog readers “Thank you for all your advices which you share on blog. I have an issue where I would like in resource pool file calculate the total “booked” work hours … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

How to avoid unnecessary Resources in MS PROJECT 2016

Hi, as you may already know, you can put Resources in MS PROJECT in many different ways. Sometimes this is good, but sometimes it can be very annoying. I will show you one example with MS PROJECT 2016! First I’m … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Predecessors, Successors and Task form in MS PROJECT 2016

Hi, How often do you have a large Project with lot of Tasks? Hundreds of them. And your schedule is very complicated. And then, suddenly you have to change something. Maybe relations within Tasks, maybe your timeline is too long, … Continue reading

Posted in Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Recording task progress ahead of schedule in MS PROJECT 2016!

Hi, my Blog reader has a problem with scheduling Task ahead of planned time! I will reproduce his scenario in MS PROJECT 2016!. First I’m going to create simple Project with two Tasks: Now I’m going to create two Resources … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

How to build Project Schedule with Task form using MS Project 2016

Hi, Today I will show you how to build schedule using Task form in MS PROJECT 2016. First I will create a simple Project: I will create two Resources: Now, it is time to create Schedule! Which Task has which … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , , , , | Leave a comment

Remaining work with Task in progress when new Resource is assigned is assigned in MS PROJECT 2016

Hi, in the first Post this year I will answer the question from one of my Blog readers: “How will MS Project calculate remaining work, when a resource is added to a task after baseline is assigned and work has … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment