Tag Archives: Micorosft Project 2016 – Schedule

Over allocation not shown in MS PROJECT 2016 with Windows 10–Bug or not?

Hi, My blog reader has a problem. He explained it step by step, and I will answer at it in the same way. Project in certain instances doesn’t flag  over allocated resources.For example, I created a resource John and assigned … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 1 Comment

Multiple relationships between Tasks – using dummy Task in MS PROJECT 2016

Hi, my last post Multiple relationships between Tasks–is this possible?, caused a lot of reactions. all of them are about using dummy Task. Here is one of them: “Insert a dummy milestone to carry part of the logic between the … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , | 2 Comments

Multiple relationships between Tasks–is this possible?

Hi, I have a great question form one of my Blog readers: “Hi Nenad, thanks for your time and experience. I have a question:I have to tasks 1 and 2.Task 2 starts with 1 day of delay of the start … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2016 | Tagged , | 4 Comments

Scheduled Start and Scheduled Finish fields in MS PROJECT 2016

Hi, today I will explain two fields, not so often used in MS PROJECT 2016: Scheduled Start and Scheduled Finish. First I will create one simple Project with three Tasks, connected like this: As you can see Scheduled Start is … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

How to show duration in different units for the same Task in MS PROJECT 2016

Hi, today I’m going to show you ProjDurConv function which is very useful in MS PROJECT 2016. Here is the Scenario. Suppose that I have a simple Project with one Task, and it’s Duration is 5 days: I want to … Continue reading

Posted in Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

New way of choosing Predecessors and Successors in MS PROJECT 2016

Hi, If you work with the latest version of MS PROJECT 2016, and you have update it regular you will notice one great improvement in Predecessor field. Let me show you that. First I will create brand new Project with … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 1 Comment

Multiple assignments on the same Task in MS PROJECT 2016

  Hi, my Blog Reader has a very interesting question: “Hi Nenad I have a problem, and I hope you can help me, I’m a follower of your blog. I have some task on project and resources, but I want … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment