Tag Archives: Micorosft Project 2016 – Schedule

Units field in Resource assignment – MS PROJECT 2016

Hi, I’ve got a question from one of my Blog readers: “Max units field in Assign Resources are always in %? I want to use QTY instead of %, like we have 10 cranes available, and how many cranes are … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Task Calendar in MS PROJECT 2016 – the right way to use it

Hi, as we all know, there are three types of Calendars in MS PROJECT 2016: Base Calendars, Resource Calendars and Task Calendars. they are prioritized in that order (from low to high importance), which means that Task Calendar has  the … Continue reading

Posted in Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Move vs Update Tasks in MS PROJECT 2016

Hi, in my last post I wrote about differences between Move and Update options in MS PROJECT 2016 on the Project Level, Now it is time to explain those two different options on the Task level. First, I will create … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

% Work Completed without Resources assigned to Tasks

  Hi, I wrote several Posts about % Work completed field, and how does it change when assigned Resources to the Task. As you know, Work is 0 hours until you assign Resource to the Task. But, is it possible … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project Server 2010, MS PROJECT 2016 | Tagged , , | Leave a comment

Different weekends for Resources in MS PROJECT 2016

Hi, I have a very good question from one of my Blog Readers: “Hi! How does one fix different holidays for persons on the same activity? That is if X and Y are working on the same Project and Task … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Milestone with “Finish not later than” constraint and Float Ii n MS PROJECT 2016!

Hi guys, I have another great question from one of my Blog readers: “Hi Nenad, I have another question for you.Suppose you have a task with start date, for example, 7 Nov and 5d duration. Its successor is a finish … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Fixed duration Tasks and over allocation resolution in MS PROJECT 2016

Hi, I have interesting question form one of my Blog Readers: “I have below query in Fixed Duration Task.Step1: created a task “paint the wall” with duration as 10 days (work starts by a Monday). Task is fixed durationStep2: created … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | 2 Comments