Tag Archives: Micorosft Project 2016 – Schedule
Recording task progress ahead of schedule in MS PROJECT 2016!
Hi, my Blog reader has a problem with scheduling Task ahead of planned time! I will reproduce his scenario in MS PROJECT 2016!. First I’m going to create simple Project with two Tasks: Now I’m going to create two Resources … Continue reading
How to build Project Schedule with Task form using MS Project 2016
Hi, Today I will show you how to build schedule using Task form in MS PROJECT 2016. First I will create a simple Project: I will create two Resources: Now, it is time to create Schedule! Which Task has which … Continue reading
Remaining work with Task in progress when new Resource is assigned is assigned in MS PROJECT 2016
Hi, in the first Post this year I will answer the question from one of my Blog readers: “How will MS Project calculate remaining work, when a resource is added to a task after baseline is assigned and work has … Continue reading
Task Actual Start and Finish date when Resources are unavailable in MS PROJECT 2016
Hi, in this last post for year 2018. I will show you how Actual Start and Finish date are affected with Resource Calendar in MS PROJECT 2016. First I will crate Simple Project with one Task: I will create Two … Continue reading
Inactive Tasks and Actuals in MS PROJECT 2016
Hi, I saw very interesting discussion in LinkedIn, about making Task Inactive if it has actuals. First let me show the “issue”. I will create brand new Project in MS PROJECT 2016: and I will create John as Resource with … Continue reading
Actual duration for manually entered actual work in MS PROJECT 2016
Hi, I have a question from my Blog reader, and I’m going to explain the problem step by step. Of course I will use MS PROJECT 2016! My blog reader’s problem is written with Italic. 1. Let’s create a 5 … Continue reading
Effort without specific Tasks in Projects using Microsoft Project 2016!
Hi, often I have a question like this: “How to assign Work to someone when that work is not to be linked with any specific Task?”. I will show you how with MS PROJECT 2016! But first I have to … Continue reading
Over allocation not shown in MS PROJECT 2016 with Windows 10–Bug or not?
Hi, My blog reader has a problem. He explained it step by step, and I will answer at it in the same way. Project in certain instances doesn’t flag over allocated resources.For example, I created a resource John and assigned … Continue reading
Multiple relationships between Tasks – using dummy Task in MS PROJECT 2016
Hi, my last post Multiple relationships between Tasks–is this possible?, caused a lot of reactions. all of them are about using dummy Task. Here is one of them: “Insert a dummy milestone to carry part of the logic between the … Continue reading
Multiple relationships between Tasks–is this possible?
Hi, I have a great question form one of my Blog readers: “Hi Nenad, thanks for your time and experience. I have a question:I have to tasks 1 and 2.Task 2 starts with 1 day of delay of the start … Continue reading