Effort without specific Tasks in Projects using Microsoft Project 2016!

Hi, often I have a question like this: “How to assign Work to someone when that work is not to be linked with any specific Task?”. I will show you how with MS PROJECT 2016! But first I have to … Continue reading

Posted in Microsoft Project 2013, Micsrosoft Project 2016, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , , | Leave a comment

When and why assign Resources to Summary Tasks and Milestones in MS PROJECT 2013!

Hi, I got a question from one of my Blog Readers: “Hi, would you be so kind and explain when to assign Resource to Summary Task or Milestone!” I will explain how to do it (which is very easy), and … Continue reading

Posted in Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , | 2 Comments

Importing Resources from Excel into MS PROJECT 2013

Hi, my Blog reader has a problem: “Hi Nenad, I am Carlos Altamirano from Ecuador, South America. First of all I want to thank you very much for your always useful and concise work your are doing with your excellent … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , | 2 Comments

Changing max units field in Assign Resources window in MS PROJECT 2013

Hi, this is my last post for this year. I will show you what is happening when you change Units in Assign Resource field in MS PROJECT 2013! First, I’m going to create new Project with only one Task: and … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft SharePoint, PMI, PRoject Management | Tagged , , , , , | 5 Comments

How to add exception into Resource Calendar in MS PROJECT 2013?

Hi, here is question form one of my Blog Readers: “I want assign a task to a particular resource on a Holiday. How can I do that. For eg: I have specified December 25 th as exception in my project … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , | 1 Comment

How to apply multiple Resource Calendars to the Same Resource in MS PROJECT 2013?

  Hi, my Blog reader has a problem: “My problem is that some of resources have 2 work schedules. When they work on-shore (5 days week 8 hours day) and off-shore (7 days week and 11 hours day), For each … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , | 7 Comments

How to Assign different Overtime Rate in MS PROJECT 2013

  Hi, in one of my Posts I have explained how to calculate and work with Overtime hours in MS Project 2013, so I am not going to do it again. This time I will explain how to apply different … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , | Leave a comment