99% completed of whole Project and/or Tasks in MS PROJECT 2013
Hi, very often I receive question like: “My Task remains 99% completed, and I do not know why?”, or “All Tasks are 100% completed but the whole project is 99% completed. Why?” Hera are two most often reasons for that. … Continue reading
Actual start and finish date with material Resources in MS PROJECT 2013! When it does make a sense, and when it does not!
Hi, in this Blog Post I will show you how to use Actual Start and Finish date with Material Resources in a proper way. Of course, using MS PROJECT 2013! First I’m going to create brand new Project: As you … Continue reading
Actuals on Summary Tasks in MS PROJECT 2013
Hi, today I will answer on may questions I’ve got from my Blog Readers, regarding to entering % Complete, and Actual work in Summary Task, instead in Sub Tasks. I will do it in MS PROJECT 2013! As always, I’m … Continue reading
Manually Scheduled Summary Tasks, and Subtasks in MS PROJECT 2013
Hi, Today I will explain how to use Manually Scheduled Summary Tasks and its Subtasks in MS PROJECT 2013 First I will create new Project, and then I will create one Manually Scheduled Summary Task, like in picture below: Now … Continue reading
Maximal Units and Default Values in MS PROJECT 2013
Hi, my Blog Reader is in trouble. He wrote:”Hi Nenad, I am in need of a favor from you. I am currently working with the MS project to accomplish the team utilization and also to forecast the team’s availability. I … Continue reading
Multiple Critical Paths in MS PROJECT 2013
Hi, today I will show you how to use Option: Calculate multiple critical paths in MS PROJECT 2013! What is Critical Path indeed? This is the longest path which show you how long will a Project Duration be. It is … Continue reading
Status Date line in MS Project 2013!
Hi, I’ve got a simple question from one of my Blog readers: “Hi, in your examples I can see Status Date in a Gantt Chart View. But I can not see it in my Projects. How to get this?” The … Continue reading
Split in progress Task option in MS PROJECT 2013!
Hi, My very good friend Ben Howard, find a problem, and a solution. I will share it with you. But before you continue to read this Post please taka a look on his great site: http://www.applepark.co.uk. Do I have to … Continue reading
Updating Project to status date versus Leveling in MS PROJECT 2013
Hi, yesterday I was teaching one of my Blog Readers about Leveling and Updating Projects in MS PROJECT 2013. The main problem was that after updating Project over allocated resources are still over allocated. I will explain the difference between … Continue reading
Critical Path in Timeline View with MS PROJECT 2013!
Hi, there is a question from one MS PROJECT user: “Hi! In the MS PROJECT 2013, is it possible to have the critical path displayed in the timeline View?” This Post will be short, because it is easy to do … Continue reading