how to edit Multiple Tasks at once in MS PROJECT 2013

Hi, often you will need to edit information not only for single, but for multiple Tasks in MS PROJECT 2013, and you will not want to edit Task by Task because it is time consuming. What can you do? First … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010 | Tagged | 2 Comments

99% completed of whole Project and/or Tasks in MS PROJECT 2013

Hi, very often I receive question like: “My Task remains 99% completed, and I do not know why?”, or “All Tasks are 100% completed but the whole project is 99% completed. Why?” Hera are two most often reasons for that. … Continue reading

Posted in Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010 | Tagged , , | Leave a comment

How to create graphic indicator for Task Status in MS PROJECT 2013

Hi, here is the question from one of my Blog Reader: “Hi Nenad, You are a lifesaver my friend 🙂 many thanks .., Another question, is there anyway I can color-code the various statuses ? so if LATE then show … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 2 Comments

How to replace Resource for the partial completed Tasks in MS PROJECT 2013?

Hi, I’ve got a question from one of my Blog Readers: “Dear Nenad, I have the following scenario: I have A Task assigned with one Resource. He did 50% work, and then he left the Company. I must assign another … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 2 Comments

Fixed Duration, actual work, remaining work – how are they linked in MS PROJECT 2013?

Hi, Today I’ll show you something that looks like a bug but it is not. Suppose that you have a Task with 5 days duration, and the Task Type is Fixed duration. I’ll do that Scenario in MS PROJECT 2013! … Continue reading

Posted in Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010 | Tagged , , , , , | 2 Comments

ASAP and ALAP constraint combination in MS PROJECT 2013

Hi, my Blog Reader has a problem: “Please can you help me. I would like to know how I can ask MS project to set one task ALAP without causing successors to move ALAP as well. In other words, I … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PRoject Management | Tagged , , | Leave a comment