Tag Archives: Microsoft Project 2013 – tracking
Baseline and Overtime work in MS PROJECT 2013
Hi, as usual I have a question from one of my Blog Readers: “Dear Sir, Can you help me to solve one issue in MS Project? After finishing base line work hours, values entered to actual over time not adding … Continue reading
Fixed Duration, actual work, remaining work – how are they linked in MS PROJECT 2013?
Hi, Today I’ll show you something that looks like a bug but it is not. Suppose that you have a Task with 5 days duration, and the Task Type is Fixed duration. I’ll do that Scenario in MS PROJECT 2013! … Continue reading
How to make a right Schedule for your Project, after it begin in MS PROJECT 2013
Hi, in this post I will explain what to do with your Project when you are late, and how to make your schedule Accurate! First, I will create some Tasks in MS PROJECT 2013: Then some Resources: Finally I will … Continue reading
% Complete vs % Work Complete in MS PROJECT 2013
Hi, some people asked me about difference between %Complete, and %Work Complete. I’ll show you the difference with a very simple example in MS PROJECT 2013. First, I will create a Simple Project with a single Task: I will have … Continue reading
Tracking resources exact hours on a standard calendar in MS PROJECT 2013
Hi, Again a question from one of my Blog readers: “Dear Nenad,I really appreciate your blog…helps me immensely.I would really be grateful if you could help me on tracking resources exact hours on a standard calendar. I am interested … Continue reading