Baseline and Calendars in MS PROJECT 2013
Hi, I got a question from my Blog Reader: “Dear Nenad, I have a problem. I set up Base Calendar with exceptions. I create a Schedule, assign Resources, and I save the Baseline. But after some time I notice that … Continue reading
Milestone with Duration greater than zero days in MS PROJECT 2013!
Hi, today I will write about Milestones in MS PROJECT 2013! Before I started I would like to thank my MVP friend Oleksiy Prosnitskyy from Ukraine (http://msprojectmvp.blogspot.com/), who ALWAYS read my Blog, and he is the first who notice me … Continue reading
How to Protect your Project file with MS PROJECT 2013?
Hi, I have a lot of questions about protecting MS PROJECT 2013 files, and I will explain it here! First, I’m going to create a simple Project: and Resources: and I will assign Resources to Task: I will look ate … Continue reading
Project start time in MS Project 2013
Hi, I will show you what happens if you change default start time in MS PROJECT 2013, and how to get right Project Start date. First I will set Date format so I can see hours. Click on File Tab, … Continue reading
Posted in Microsoft Project 2013, MS PROJECT 2010
Tagged Microsoft Project 2013, MS PROJECT 2013
12 Comments
99% completed of whole Project and/or Tasks in MS PROJECT 2013
Hi, very often I receive question like: “My Task remains 99% completed, and I do not know why?”, or “All Tasks are 100% completed but the whole project is 99% completed. Why?” Hera are two most often reasons for that. … Continue reading
Actual start and finish date with material Resources in MS PROJECT 2013! When it does make a sense, and when it does not!
Hi, in this Blog Post I will show you how to use Actual Start and Finish date with Material Resources in a proper way. Of course, using MS PROJECT 2013! First I’m going to create brand new Project: As you … Continue reading
Actuals on Summary Tasks in MS PROJECT 2013
Hi, today I will answer on may questions I’ve got from my Blog Readers, regarding to entering % Complete, and Actual work in Summary Task, instead in Sub Tasks. I will do it in MS PROJECT 2013! As always, I’m … Continue reading
When and why assign Resources to Summary Tasks and Milestones in MS PROJECT 2013!
Hi, I got a question from one of my Blog Readers: “Hi, would you be so kind and explain when to assign Resource to Summary Task or Milestone!” I will explain how to do it (which is very easy), and … Continue reading
Manually Scheduled Summary Tasks, and Subtasks in MS PROJECT 2013
Hi, Today I will explain how to use Manually Scheduled Summary Tasks and its Subtasks in MS PROJECT 2013 First I will create new Project, and then I will create one Manually Scheduled Summary Task, like in picture below: Now … Continue reading
Maximal Units and Default Values in MS PROJECT 2013
Hi, my Blog Reader is in trouble. He wrote:”Hi Nenad, I am in need of a favor from you. I am currently working with the MS project to accomplish the team utilization and also to forecast the team’s availability. I … Continue reading