Tag Archives: MS PROJECT 2013
Overallocated fields in MS PROJECT 2013
Hi, today I will explain Overallocated fields in MS PROJECT 2013, because they are confusing a lot of my Blog readers. First I will create Project with three Tasks, and I will add Overallocated field in Gantt Chart View: I … Continue reading
Must Finish On constraint and Actual values in MS PROJECT 2013
Hi, I’ve got a lot of questions about Must Finish On constraint and Actual values. How MS PROJECT 2013 “reacts” on different actuals whet Task has MFO Constraint. I will create very simple Project: and for the Task I will … Continue reading
How to Protect your Project file with MS PROJECT 2013?
Hi, I have a lot of questions about protecting MS PROJECT 2013 files, and I will explain it here! First, I’m going to create a simple Project: and Resources: and I will assign Resources to Task: I will look ate … Continue reading
Project start time in MS Project 2013
Hi, I will show you what happens if you change default start time in MS PROJECT 2013, and how to get right Project Start date. First I will set Date format so I can see hours. Click on File Tab, … Continue reading
Posted in Microsoft Project 2013, MS PROJECT 2010
Tagged Microsoft Project 2013, MS PROJECT 2013
12 Comments
Manually Scheduled Summary Tasks, and Subtasks in MS PROJECT 2013
Hi, Today I will explain how to use Manually Scheduled Summary Tasks and its Subtasks in MS PROJECT 2013 First I will create new Project, and then I will create one Manually Scheduled Summary Task, like in picture below: Now … Continue reading
Changing max units field in Assign Resources window in MS PROJECT 2013
Hi, this is my last post for this year. I will show you what is happening when you change Units in Assign Resource field in MS PROJECT 2013! First, I’m going to create new Project with only one Task: and … Continue reading
How to Move Project when Project has Manually Scheduled Tasks and/or Constraints in MS PROJECT 2013
Hi, I’ll how you how to move Project when it has Manually Scheduled Tasks or Constraints in MS PROJECT 2013 First I will make a simple Project with no manually Scheduled Tasks or Constraints. Now suppose that your plan is … Continue reading
How to update Baseline and Save actual data in MS PROJECT 2013?
Hi, I have a question from my Blog reader: “Hi, How can I update Baseline with new Tasks if Project has Tasks with Actual data, e.g I don’t want to loose those actual data, nor I want to change Baseline … Continue reading
How to replace Resource for the partial completed Tasks in MS PROJECT 2013?
Hi, I’ve got a question from one of my Blog Readers: “Dear Nenad, I have the following scenario: I have A Task assigned with one Resource. He did 50% work, and then he left the Company. I must assign another … Continue reading
% Complete vs. Finish Date in MS PROJECT 2013
Hi, here is another problem from one of my Blog readers: “Hi Nenad – allow me to give you an example of my problem. A task with a finish date of May 5/14 has a % complete of 25%. When … Continue reading