Changing max units field in Assign Resources window in MS PROJECT 2013
Hi, this is my last post for this year. I will show you what is happening when you change Units in Assign Resource field in MS PROJECT 2013! First, I’m going to create new Project with only one Task: and … Continue reading
How to Move Project when Project has Manually Scheduled Tasks and/or Constraints in MS PROJECT 2013
Hi, I’ll how you how to move Project when it has Manually Scheduled Tasks or Constraints in MS PROJECT 2013 First I will make a simple Project with no manually Scheduled Tasks or Constraints. Now suppose that your plan is … Continue reading
How to update Baseline and Save actual data in MS PROJECT 2013?
Hi, I have a question from my Blog reader: “Hi, How can I update Baseline with new Tasks if Project has Tasks with Actual data, e.g I don’t want to loose those actual data, nor I want to change Baseline … Continue reading
Scheduled Duration, Start and Finished Date in MS PROJECT 2013
Hi, A question from my Blog reader is: “Please clarify the purpose of fields Schedule Duration, Schedule Start & Schedule Finish. In which context they are used and how they differ from Duration, Start & Finish Fields ?” I will … Continue reading
How to replace Resource for the partial completed Tasks in MS PROJECT 2013?
Hi, I’ve got a question from one of my Blog Readers: “Dear Nenad, I have the following scenario: I have A Task assigned with one Resource. He did 50% work, and then he left the Company. I must assign another … Continue reading
The Resume fields in MS PROJECT 2013
Hi, Imagine this situation: you have a Task with one Resource, and duration is 5 days. The task is on Track, and it is 50% completed. Suddenly, Resource get sick, and will be able to continue with work after few … Continue reading
Strange Duration in MS PROJECT 2013 – Bug or Not!
Hi, I will show you something that makes MS PROJECT users crazy! Of course I’ll use MS PROJECT 2013. I will first, create a Brand new Project with one Task with 5 days Duration, like this: Everything is just fine. … Continue reading
Status field in MS PROJECT 2013
Hi, today I’ll show you how Status field works in MS PROJECT 2013. As usual I am going to Create some Tasks: I will add the Status field in the View: ¸ As you can see Task 1 is … Continue reading
Actual finish date in MS PROJECT 2013
Hi, again, one of by Blog readers has a question: “How do you update actuals? Let’s say the task is supposed to have finished 21 Feb 2014 according to the original plan. However, this task can now be finished … Continue reading
Multiple Critical Paths in MS PROJECT 2013
Hi, we all know what Critical Path means. It is path in which, if any Activity is late, the whole Project is late. Let me show you Critical Path in MS PROJECT 2013. First I’ll create new Project with some … Continue reading