Tag Archives: MS PROJECT 2010

Changing max units field in Assign Resources window in MS PROJECT 2013

Hi, this is my last post for this year. I will show you what is happening when you change Units in Assign Resource field in MS PROJECT 2013! First, I’m going to create new Project with only one Task: and … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft SharePoint, PMI, PRoject Management | Tagged , , , , , | 5 Comments

How to Move Project when Project has Manually Scheduled Tasks and/or Constraints in MS PROJECT 2013

Hi, I’ll how you how to move Project when it has Manually Scheduled Tasks or Constraints in MS PROJECT 2013 First I will make a simple Project with no manually Scheduled Tasks or Constraints. Now suppose that your plan is … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | Leave a comment

How to update Baseline and Save actual data in MS PROJECT 2013?

Hi, I have a question from my Blog reader: “Hi, How can I update Baseline with new Tasks if Project has Tasks with Actual data, e.g I don’t want to loose those actual data, nor I want to change Baseline … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 9 Comments

Scheduled Duration, Start and Finished Date in MS PROJECT 2013

Hi, A question from my Blog reader is: “Please clarify the purpose  of fields Schedule Duration, Schedule Start & Schedule Finish. In which context they are used and how they differ from Duration, Start & Finish Fields ?” I will … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , , | Leave a comment

How to replace Resource for the partial completed Tasks in MS PROJECT 2013?

Hi, I’ve got a question from one of my Blog Readers: “Dear Nenad, I have the following scenario: I have A Task assigned with one Resource. He did 50% work, and then he left the Company. I must assign another … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 2 Comments

The Resume fields in MS PROJECT 2013

Hi, Imagine this situation: you have a Task with one Resource, and duration is 5 days. The task is on Track, and it is 50% completed. Suddenly, Resource get sick, and will be able to continue with work after few … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | Leave a comment

Strange Duration in MS PROJECT 2013 – Bug or Not!

Hi, I will show you something that makes MS PROJECT users crazy! Of course I’ll use MS PROJECT 2013. I will first, create a Brand new Project with one Task with 5 days Duration, like this: Everything is just fine. … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , , | 1 Comment