Tag Archives: MS PROJECT 2013 – TASKS!
The Resume fields in MS PROJECT 2013
Hi, Imagine this situation: you have a Task with one Resource, and duration is 5 days. The task is on Track, and it is 50% completed. Suddenly, Resource get sick, and will be able to continue with work after few … Continue reading
Task Calendar in MS PROJECT 2013 – when to use it?
Hi, Again, I have a request (question) from one of my Blog readers: ! “Hello, Your tutorials are very helpful – thank you! I was wondering if it is possible to make a particular task not allowed on a particular … Continue reading
Inactive Tasks in MS PROJECT 2013
Hi, this Post will be a really short one! I’m going to explain how Inactive Task is different in MS PROJECT 2013. First, notice that this functionality is available only with MS PROJECT 2013 PROFESSIONAL version. I’ll create new Project,first: … Continue reading
Work Package versus Activity in MS PROJECT 2013
Hi, another question from one of my Blog Readers: “Hello; I have a question about “work package”. Is work package the same as “activity” or “activity” is more detailed than a work package? Thank you” Theory first. Suppose that … Continue reading
Effort and non effort driven Tasks in MS PROJECT 2013
Hi, here is the question from my Blog reader: “Nenad:Thanks very much for the posting! Do you know if there is any way of setting up a different default for this operation? More specifically, suppose that I have many … Continue reading