Tag Archives: MS PROJECT 2010 – Scheduling

Duration, Units, Work and Schedule in MS PROJECT 2013. How are they linked, and some tips and tricks!

Hi, this is my first Post in this year and it will be a quite long. Again, one of my Blog readers ha a problem, and this problem is about scheduling. Here it is: “Dear Nenad,Glad to find your site … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI | Tagged , , , , , | 5 Comments

Scheduled Duration, Start and Finished Date in MS PROJECT 2013

Hi, A question from my Blog reader is: “Please clarify the purpose  of fields Schedule Duration, Schedule Start & Schedule Finish. In which context they are used and how they differ from Duration, Start & Finish Fields ?” I will … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management | Tagged , , , , , | Leave a comment

The Resume fields in MS PROJECT 2013

Hi, Imagine this situation: you have a Task with one Resource, and duration is 5 days. The task is on Track, and it is 50% completed. Suddenly, Resource get sick, and will be able to continue with work after few … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | Leave a comment

Scheduling Problem in MS PROJECT 2013

Hi, again a question from one of My Blog Readers: “What if you work 9 hrs per day mon to thurs and 8 hrs per day friday for week 1, and for week 2 you work 9 hrs per day … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft SharePoint, PMI | Tagged , , , , , | 2 Comments

Task Types and how they affect the Schedule–Part 1

  Hi, In next few posts I will explain task types and how do they reflect on Schedule in MS PROJECT 2010. Basically, there art three Task Types: Fixed Units (Default) Fixed Work Fixed Units What are those? Units or … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , , | 15 Comments

The “Wedding” Project! Building the Schedule? – PART 4

  Hi, If you remember I had (and I still have) a problem with my “wedding” project. I set up a Wedding Saturday , and Wedding Sunday Task Calendars in MS PROJECT 2010. As I said many times before I … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 1 Comment

The “Wedding” Project! Building the Schedule? – PART 2

  Hi, this post might be very boring! Because I am using the “Wedding” project I will put duration for each and every task! There are 100 task and I had to explain why I put those duration for each … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 1 Comment