Hi,
again a question from one of My Blog Readers:
“What if you work 9 hrs per day mon to thurs and 8 hrs per day friday for week 1, and for week 2 you work 9 hrs per day mon to thursday, no work on fri. So week 1 is 44 hrs and week 2 is 36 hrs. I can specify all this in the working calendar, but in the scheduling options, you can only choose a certain no of hrs per day, and a certain no of hrs per week, and this would differ from the working calendar, which would lead to errors. What’s you advice on such a situation?”
Ufffff! Let’s start with MS PROJECT 2013! First of all:
then:
and:
Notice that it is 8 Hours Per Day!
Now I am going to rearrange Standard Calendar:
and:
I do not have to do anything for Friday/12/13/2013, because it is already scheduled as 8 hour working day.
I’m going to set up second week:
Finally I’ll set Friday/12/20/2013 as a non working day:
Now, I’ll add Task with 10 days Duration:
and I’ll assign John (who works on Standard Calendar) to the Task:
After Assigning John To Task 1I’ll get:
Now, let’s take a look at the Task Usage View:
Let me explain:
Because I said that one day will have 8 hours for working (look at the top of this Post) the Calculation is: This Task 1 needs 10 days of duration * 8 hours per day = 80 hours. So, for completing this Task we will need to work 80 hours on it! Because John will work on Standard Calendar he will work first week from Monday to Thursday 9 hours per day (4*9=36 hours), 8 hours on Friday, which is 36+8=44 hours at First week, and Second week he will work 9 hours per day (from Monday to Thursday, 4*9=36 hours), and he will not work on Friday. Total is: 44 hours at first week + 36 hours at second week = 80 hours.
This is how MS PROJECT works! What will be if I change in Scheduling options that it is 9 hours per day:
Back to the Task Usage View:
Because I said that one day will have 9 hours for working (look at the top of this Post) the Calculation is: This Task 1 needs 10 days of duration * 9 hours per day = 90 hours. So, for completing this Task we will need to work 90 hours on it! Because John will work on Standard Calendar he will work first week from Monday to Thursday 9 hours per day (4*9=36 hours), 8 hours on Friday, which is 36+8=44 hours at First week, and Second week he will work 9 hours per day (from Monday to Thursday, 4*9=36 hours), and he will not work on Friday. Total is: 44 hours at first week + 36 hours at second week = 80 hours. We need 10 hours more to complete this Task, So John will work 8 hours at Monday and 2 hours at Tuesday at third week.
Be very careful! When you change working hours from 8 to 9, for example, all Tasks will be affected by that.
So that’s it! I hope that this explains MS PROJECT behavior
Regards!
Dear Sir,
I am looking for answer about wrong durations in Ms-Project 2013. I placed the duration for 10 days and get the start and finish date difference equals to 12 days though as per calender it should be 11 days. Kindly advice why it is behaving like this
Please send me an mpp file to nenadtrajk@gmail.com and tell me which Task ID are you talking about?