Tag Archives: Microsoft Project 2013 – Scheduling
Multiple Critical Paths in MS PROJECT 2013
Hi, today I will show you how to use Option: Calculate multiple critical paths in MS PROJECT 2013! What is Critical Path indeed? This is the longest path which show you how long will a Project Duration be. It is … Continue reading
Split in progress Task option in MS PROJECT 2013!
Hi, My very good friend Ben Howard, find a problem, and a solution. I will share it with you. But before you continue to read this Post please taka a look on his great site: http://www.applepark.co.uk. Do I have to … Continue reading
Duration with different Resources working time in MS PROJECT 2013!
Hi, with permission of my MVP friend Gérard Ducouret I will explain how different Resources working time affect Task duration in MS Project 2013! I will show you on the example. First, I will create (as I always do), the … Continue reading
Updating Project to status date versus Leveling in MS PROJECT 2013
Hi, yesterday I was teaching one of my Blog Readers about Leveling and Updating Projects in MS PROJECT 2013. The main problem was that after updating Project over allocated resources are still over allocated. I will explain the difference between … Continue reading
Reschedule uncompleted work and SNET constraint in MS PROJECT 2013
Hi, I have a question form my Blog Reader: “Hi NenadI have the issue. My tasks are all set to automatically scheduled. I update actuals weekly and once completed I update the project and select ‘reschedule uncompleted work to start … Continue reading
Lead time in relative Terms with MS PROJECT 2013
Hi, Lead is time which allow Successor Task to start before Predecessor is finished, and still keep Finish To Start relationship. I wrote about that in my Blog Post: https://ntrajkovski.com/2011/04/12/scheduling-problems-in-ms-project-2010-part-2/ Let’s see how to make it relative in MS PROJECT … Continue reading
How to set Resources to work at different time with different amount of work at the same Task in MS PROJECT 2013
Hi, I have a question from one of my Blog Readers: “” “Nenad, I have two Resources on the same Task. I want to assign them at different time and different work. Let’s say that John will work 40 hours … Continue reading
Duration, Units, Work and Schedule in MS PROJECT 2013. How are they linked, and some tips and tricks!
Hi, this is my first Post in this year and it will be a quite long. Again, one of my Blog readers ha a problem, and this problem is about scheduling. Here it is: “Dear Nenad,Glad to find your site … Continue reading
Crashing and Fast Tracking in MS PROJECT 2013
Hi, in this Post I will introduce two Terms: Crashing and Fat Tracking. When your Schedule is too long, and you want to short it, you will can add additional Resources to Tasks (and this is called Crashing), or you … Continue reading
Slack and Microsoft Project 2013
Hi, again my Blog reader has a problem: “Hi,I have a question about Slack, I am preparing a construction schedule for my small project and using M.S.P. the problem I have is, when I active the slack on the schedule, … Continue reading