Tag Archives: Microsoft Project 2013 – Scheduling

Rescheduling Project or Tasks, and Constraints in MS PROJECT 2013

Hi, my Blog reader ha a question: “Dear Nenad, After  we update the  progress (% Complete) on various tasks on a baselined project, I understand we need to re-schedule  the uncompleted work to start after the status date. This is … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PRoject Management | Tagged , , | 2 Comments

Task are not Scheduled as expected in MS PROJECT 2013

My Blog reader has a problem: “Hi Nenad. I am creating a simple Project with four Tasks. Task 1 is predecessor for Task 2, etc. I do not have a right Schedule, and they all start at the same date. … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | Leave a comment

The Resume fields in MS PROJECT 2013

Hi, Imagine this situation: you have a Task with one Resource, and duration is 5 days. The task is on Track, and it is 50% completed. Suddenly, Resource get sick, and will be able to continue with work after few … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | Leave a comment

Scheduling Problem in MS PROJECT 2013

Hi, again a question from one of My Blog Readers: “What if you work 9 hrs per day mon to thurs and 8 hrs per day friday for week 1, and for week 2 you work 9 hrs per day … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft SharePoint, PMI | Tagged , , , , , | 2 Comments