Rescheduling Project or Tasks, and Constraints in MS PROJECT 2013

Hi,

my Blog reader ha a question:

Dear Nenad,

After  we update the  progress (% Complete) on various tasks on a baselined project, I understand we need to re-schedule  the uncompleted work to start after the status date.

This is required to  prevent the ambiguity of certain tasks with 0%  progress to start earlier than the status date.

The   Re-schedule   uncompleted work  button  under Update project  in MS Project has two options Entire Project  or  Selected Tasks.

Please  clarify when to use which of the options.

Also  when we   hit the re-schedule button , the Schedule Start  date for the tasks with 0%  progress  moves to a date later to Status Date and a SNET date constraint is imposed.

Moving  forward,   do  we need to retain the SNET constraints?

My understanding is, we need to remove the SNET constraints   by  adding lags to the predecessors and match with the SNET dates.

I feel this is essential  to obtain an accurate critical path as any   date constraints  imposed on the tasks  may hamper an accurate critical path.

Please  clarify.

First I will create brand new Project in MS PROJECT 2013:

image

For Task 5 I will put  Constraint Start No earlier than 14.11.2014:

image

Now, I’m going to save my Project Plan as a Baseline:

image

and then:

image

and I will show Tracking Gantt View:

image

Now suppose that Task 1 and Task 2 are 100% finished, Task 3 is 50% finished, and Task 4 and Task 5 are 0% Finished:

image

OK. Now suppose that Status date is Friday, 21.11.2014:

image

What is done is done! I mean, time has passed, and I have to move my Project to the Status date to have real Plan. I will use Update Project:

image

and I will get:

image

Notice this:

  1. Task 1, and Task 2 are as they were
  2. Task 3 has split.  50% (finished) remains as it is, and another 50% (unfinished) has been moved to Monday, 24.11.2014 (After Status date)
  3. Task 4, and Task 5 are moved as well. Task 4, and Task 5 have new Start no earlier than Constraint which is now Friday, 21.11.2014 (Status Date). You can remove them if you don’t need them.

And it works as it should be.

Now about last question. When to Reschedule entire project and when just Selected Tasks? It is easy. Let’s look again our Project before rescheduling:

image

Now suppose that we do not have information about Task 3, and Task 4. Maybe there are finished on time, but we do not know this yet. We set the status date. And we do know that Task 5 has 0% Complete at the status date. So I will reschedule only Task 5:

image

and I will get:

image

As you can see only Task 5 is rescheduled.

So use Selected Tasks only when you know that those Tasks should be rescheduled. If your Project is up to  date with Actual % Complete, and you want to have Realistic Schedule, Reschedule the whole Project!

 

Hope this helps!

 

Regards!

Advertisement

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PRoject Management and tagged , , . Bookmark the permalink.

2 Responses to Rescheduling Project or Tasks, and Constraints in MS PROJECT 2013

  1. Alley says:

    Excellent thanks Nenad!

  2. Erik van Hurck says:

    Hi Nenad,

    Long Time since we chatted. How are you?

    I created a resource page on my blog with a link to your site. Hope you like what I say about your blog: Bit.ly\tpc_resources

    Kind regards, Erik The project corner

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s