-
Recent Posts
Archives
Categories
Blogroll
Category Archives: Microsoft PRoject 2010
Costs for no work done in MS PROJECT 2016
Hi, again my Blog reader has a problem, which is: “I have a question. Let’s say I have 4 hours of delay against a project as “ALL RESOURCES” had to wait for a crane to arrive before work could commence. … Continue reading
Resource capacity in Hours with MS PROJECT 2016 – is it possible?
Hi, my Blog Reader has a question: “I have a project plan with certain milestones which are to be completed on specific dates and I have resources assigned. But as per plan, the resource allocation hours are reduced whereas in … Continue reading
How to change Resource Assignments for Multiple Tasks in MS PROJECT 2016
Hi, Here is a problem that one of my Blog Readers have: “Is there a way to have the same resource – Team A work on multiple tasks and a place where I can change the “Units %” from 300% … Continue reading
Resource calendar vs. Task Calendar, and weekends in MDS PROJECT 2016
Hi, Again, I have a question from one of my Blog readers, which is related to my previous post: “Hi Nenad,¸ Thank you very mush. But can you please explain the following inconsistency in MSP behavior: If in the example … Continue reading
How to delete all dependencies for one Task in MS PROJECT 2016
Hi, for the last post in this year I choose to show you a very simple Trick. What if you have one Task with multiple Tasks dependencies, and, for some reason you want to remove those dependencies in one step. … Continue reading
Fixed duration Task and Resource Calendar
Hi, today I will explain how is Work field Calculated when you have Fixed Duration Task Type, and Resource Calendar. Of, course I will use MS PROJECT 2016! First, as I always do, I will create new Project with a … Continue reading
Baseline and deleted Tasks in MS PROJECT 2013
Hi, I got a lot of questions about differences, for example, in Task Table when Project has Baseline, and The Task is deleted. I will show you what do in MS PROJECT 2013! First, I will crate very Simple Project: … Continue reading
Effort estimate in hours with MS PROJECT 2013
Hi, I’ve got a lot of questions like this one: “Hi, you have a lot of examples with estimating Durations! But we are estimate in hours. We don’t know Duration, but how many hours are needed to complete our Tasks! … Continue reading
how to edit Multiple Tasks at once in MS PROJECT 2013
Hi, often you will need to edit information not only for single, but for multiple Tasks in MS PROJECT 2013, and you will not want to edit Task by Task because it is time consuming. What can you do? First … Continue reading
How to Protect your Project file with MS PROJECT 2013?
Hi, I have a lot of questions about protecting MS PROJECT 2013 files, and I will explain it here! First, I’m going to create a simple Project: and Resources: and I will assign Resources to Task: I will look ate … Continue reading