Resource capacity in Hours with MS PROJECT 2016 – is it possible?

Hi,

my Blog Reader has a question:

“I have a project plan with certain milestones which are to be completed on specific dates and I have resources assigned. But as per plan, the resource allocation hours are reduced whereas in my estimation they are way higher. Is there a way where I can fix hours to the resources and then they get allocated accordingly for the tasks I assign those resources to. Let me know if there’s any other turnaround for the same”

Where is problem here? If you have, for example, John as Resource in your Project, can you have his capacity in hours? And, on the other hand, how to put exact number of hours per Task which are needed to fulfill the Task?

Let me answer to the first question. Simply – NO! You can not have capacity in MS  PROJECT 2016 (or other versions) in hours. You can have them only in Units%.

Let me create very Simple Project:

image

Now, let me create two resources for this Project:

image

As you can see John has 100% Max units. That mean that if he assigned 100% for Task he is able to work, for example, 8 hours per day (according to working calendar). On the other hand, Mary has only 50% Max units for this Project, so she can work only half of his working hours (again, according to her Calendar). If I assign John to the Task with more than 100%, and Mary with more than 50%, then they will became over allocated. Of course if I assign John with 100% to the Task, and again to another Task with, for example, 20%, and those Tasks are supposed to be executed on the same time, he will also became over allocated.

But there is no field in which I can put capacity in hours. That lead me to another question: “How to put exact number of hours per Task which are needed to fulfill the Task?

Here I have an easy answer. If you know exact number of hours for the Task must be spent by John and Mary to complete it, simple make this Tasks as Fixed work type, and assign number of hours to John and Mary. Let’s say that John need 40 hours to complete Task 1, and Mary 32.

image

and then:

image

and I will get (I will use Task usage View):

image

As you can see, Duration is now 8 days, because Mary has to work 32 hours, and she will work only 4 hours per day (because 50% of her Units), so the Task will have 4 hours per day * 8 days = 32 hours

To conclude, if you know exact number of hours that Resources must spend to complete the Task, always use FIXED WORK, and assign those hours for each resources.

Regards!

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management and tagged , , . Bookmark the permalink.

Leave a comment