Actual Duration, Actual work and Fixed work Tasks in MS PROJECT 2016

Hi,

here is one problem that my Blog Reader has (I will go step by step, and I will use MS PROJECT 2016)

“When multiple resources are assigned to the task, for a given Total Work we can  calculates the   Duration either as Work divided by  Total Assignment Units   OR  by calculating the Duration for each individual resource  as Duration (Ri) = Work (Ri) / Units (Ri))  and then selecting the longest duration of the driver resource to be a task Duration. For example, let’s say we have a 3d, 36 hr task for 2 resources R1(100%)  and R2(50%)”

image

As you can see task is Fixed work type, and I put 3 days in the Duration.

Now I am going to create two Resources, one with 100% units, and other with 50%:

image

and I’m going to assign both Resource to Task:

image

What is wrong with this Scenario. Technically nothing, but logically, if you have Fixed Work Task, it means that work is fixed, and that you know how much work you need for the Task. An, in this scenario, you should not put Duration, but Work. But, let’’ me continue with scenario from my Blog reader, and I’m going to show you Task Usage View:

image

As you can see R1 should work 3 days and 8 hours per day which is 100%, and it equals 24 hours. On the other hand, R2 should work 3 days and 4 hours per day which is 50%, and it equals 12 hours.

My Blog reader continues with: “Now I enter Actual Work of 10h into resource R1  and we get:”

image

The question from my Blog reader is:

“So we can’t anymore use the same approach to calculate Actual Duration using the Actual Work and Units of individual assigned resources. That is, if we calculate the Actual  Duration using the only Actual Work R1 we will get:
Actual Duration = Actual Work (R1) / Units (R1) = 10h / 100% = 1.25d which is not what shown on the screenshot above (0.83d).
So the only way to get Actual Duration right is to calculate it as:
Actual Duration =  Sum of Actual Work of each resource /  Total Units =( 10h + 0h) / (100% + 50%) = 10h/150% = 0.83d

So why is  the method of calculating the task  Duration based on the individual resource Work and Units  with subsequent selection of the longest duration doesn’t work for an Actual Duration calculations?“

Well, Microsoft Project does not calculate Actual Duration in that way. Let’s take a look on the right side of the Task Usage View:

image

As you can see:

  • At Monday Work was 12 hours, and Actual Work is 8 hours (Because R1 works only 8 hours per day). Actual Duration is: Actual work / Work = 8 /12 = 0,66666
  • At Tuesday Work was 12 hours, and Actual Work is 2 hours (Because R1 works remaining 2 hours of 10 hours assigned as Actual work). Actual Duration is: Actual work / Work = 2 /12 = 0,16666
  • So Actual Duration is 0,6666 + 0,16666 = 0,83 Days!

So that is Actual Duration for the Task. And it is always calculated with work and Actual work of all Resources, not one by one!

Regards!

Advertisement

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft Project 2013, MS PROJECT 2010, MS PROJECT 2016, PMI, PRoject Management and tagged , . Bookmark the permalink.

1 Response to Actual Duration, Actual work and Fixed work Tasks in MS PROJECT 2016

  1. Alex Shafir says:

    Thank you Nenad.
    Great post.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s