Category Archives: MS PROJECT 2016

Changing Values in Project Summary Tasks in MS PROJECT

Hi, Today I am going to show you how to change Duration or Start/Finish date on Summary Task using MS PROJECT 2019. I am going to create simple Project with tow Tasks under one Summary Task, and I’m going to … Continue reading

Posted in MS PROJECT 2016, MS PROJECT 2019, PMI, PRoject Management | Tagged , | Leave a comment

Resource replacement whit already assigned resource on Task in Progress–MS PROJECT!

Hi, I’ve got a question from one of my blog readers: “Let’s suppose that I have a task “Task” with fixed work task type. Duration is 10 days. I assign 2 resource who work for 8hr per day. Total work … Continue reading

Posted in Micsrosoft Project 2016, MS PROJECT 2016, PMI | Tagged , , | 1 Comment

Fixed cost for resource over the time period in MS PROJECT 2016

Hi, I’ve got a question from one of my Blog readers: “Mr. Nenad, I have a question please:Let’s suppose that I have a human work resource assigned to different tasks within the project. It receive each month a fixed salary … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Resource detail form in MS PROJECT 2016

Hi, as I wrote many times there is a very useful Task form in MS PROJECT 2016! Here is one simple project: With the Task form we have full control over the Task, like this: In Task form we can … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

Duration and % completed–relation between them in MS PROJECT 2016

Hi, I noticed that lot of MS Project users have a problem with Duration and work which was already completed. Let me give you an example in MS PROJECT 2016. Let’s say that we have a one Task Project, with … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Total hours limit with multiple Projects using MS PROJECT

Hi, I have a question from one of my Blog readers “Thank you for all your advices which you share on blog. I have an issue where I would like in resource pool file calculate the total “booked” work hours … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

Recording task progress ahead of schedule in MS PROJECT 2016

Hi, today I am going to clarify one important thing which bothers a lot of  of my Blog readers. I will go step by step through example and explain them. First I’m going to build simple Project: Now I will … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , | 1 Comment