Delay on Task in progress with MS PROJECT 2016

Hi, today I’m going to show you where is the difference between Task in progress and delay, with MS PROJECT 2016. Let’s say that we have a simple Project with one single Task: and that we have John as Resource: … Continue reading

Posted in Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

Costs for no work done in MS PROJECT 2016

Hi, again my Blog reader has a problem, which is: “I have a question. Let’s say I have 4 hours of delay against a project as “ALL RESOURCES” had to wait for a crane to arrive before work could commence. … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

How to build Project Schedule with Task form using MS Project 2016

Hi, Today I will show you how to build schedule using Task form in MS PROJECT 2016. First I will create a simple Project: I will create two Resources: Now, it is time to create Schedule! Which Task has which … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , , , , | Leave a comment

Costs in Task Form combined with Gantt Chart View in MS PROJECT 2016

Hi, Task Form is very useful thing in MS PROJECT 2016, and it can be use in various ways. Today I’ll show how to see Costs for Task per Resource. First I will create simple new Project: Now I Will … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

Remaining work with Task in progress when new Resource is assigned is assigned in MS PROJECT 2016

Hi, in the first Post this year I will answer the question from one of my Blog readers: “How will MS Project calculate remaining work, when a resource is added to a task after baseline is assigned and work has … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

How to hold Total Hours of work per Task when Actual Work is less then estimated hours in MS PROJECT 2016?

Hi, Today I’m going to explain how to solve a problem which one of my Blog Readers have in MS PROJECT 2016. Let us say that we have a Project with Task which is 6 weeks long. For this Task … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016 | Tagged , , | Leave a comment

The Agile field in Microsoft Project online

Hi, In Microsoft Project Online, there is a new Field – Agile! I will show you what can you (or can’t) do with it! First I will create brand new Waterfall Project: and I will get: As you can see, … Continue reading