Category Archives: MS PROJECT 2016
How to avoid unnecessary Resources in MS PROJECT 2016
Hi, as you may already know, you can put Resources in MS PROJECT in many different ways. Sometimes this is good, but sometimes it can be very annoying. I will show you one example with MS PROJECT 2016! First I’m … Continue reading
Predecessors, Successors and Task form in MS PROJECT 2016
Hi, How often do you have a large Project with lot of Tasks? Hundreds of them. And your schedule is very complicated. And then, suddenly you have to change something. Maybe relations within Tasks, maybe your timeline is too long, … Continue reading
Project Management Task in MS PROJECT 2016
Hi, very often I hear a question like: “OK Nenad, you are explaining how to make a good schedule, and how to assign Resources properly to Tasks!. But what about Task which are impossible to plan upfront, like, for example, … Continue reading
“Real” daily work on Tasks in MS PROJECT 2016!
Hello, today I’m going to deal whit one significant question which basically has many answers, or none. How many hours to assign to Resource per day? Let me show you one very, very simple example. Let’s say that we have … Continue reading
Project management Task and Administrative work in MS PROJECT 2016
Hi, my blog reader has a question about Project management Task, and administrative work, and how to handle it in MS PROJECT 2016? Here is Scenario. This is Project Schedule: First of all, I will advice not to use Project … Continue reading
Fixed work Task Type with limited Resource availability in MS PROJECT 2016!
Hi, my Blog reader run into problem with limited Resource availability. I will show the scenario and explain it with MS PROJECT 2016. I will create simple Project with one Task, 4 day duration, and I will assign John to … Continue reading
How to “loan” Resources from non-critical to critical Tasks in MS PROJECT 2016
Hi, today I will explain one specific Case which one of my Blog users have. And I will do it by reproducing this Case step-by-step, using MS PROJECT 2016! There are three tasks with resources assigned to them: I will … Continue reading
Delay on Task in progress with MS PROJECT 2016
Hi, today I’m going to show you where is the difference between Task in progress and delay, with MS PROJECT 2016. Let’s say that we have a simple Project with one single Task: and that we have John as Resource: … Continue reading
Costs for no work done in MS PROJECT 2016
Hi, again my Blog reader has a problem, which is: “I have a question. Let’s say I have 4 hours of delay against a project as “ALL RESOURCES” had to wait for a crane to arrive before work could commence. … Continue reading
How to build Project Schedule with Task form using MS Project 2016
Hi, Today I will show you how to build schedule using Task form in MS PROJECT 2016. First I will create a simple Project: I will create two Resources: Now, it is time to create Schedule! Which Task has which … Continue reading