Tag Archives: Microsoft Poject 2016 – Work

Duration and % completed–relation between them in MS PROJECT 2016

Hi, I noticed that lot of MS Project users have a problem with Duration and work which was already completed. Let me give you an example in MS PROJECT 2016. Let’s say that we have a one Task Project, with … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Total hours limit with multiple Projects using MS PROJECT

Hi, I have a question from one of my Blog readers “Thank you for all your advices which you share on blog. I have an issue where I would like in resource pool file calculate the total “booked” work hours … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , | Leave a comment

“Real” daily work on Tasks in MS PROJECT 2016!

Hello, today I’m going to deal whit one significant question which basically has many answers, or none. How many hours to assign to Resource per day? Let me show you one very, very simple example. Let’s say that we have … Continue reading

Posted in MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

How to hold Total Hours of work per Task when Actual Work is less then estimated hours in MS PROJECT 2016?

Hi, Today I’m going to explain how to solve a problem which one of my Blog Readers have in MS PROJECT 2016. Let us say that we have a Project with Task which is 6 weeks long. For this Task … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016 | Tagged , , | Leave a comment