Duration with different Resources working time in MS PROJECT 2013!

Hi,

with permission of my MVP friend Gérard Ducouret I will explain how different Resources working time affect Task duration in MS Project 2013!

I will show you on the example. First, I will create (as I always do), the brand new Project:

image

I will create two Resources, one will work 8 hours per day, and the other 7 hours per day:

 image

I will now change Standard Calendar for Resource – 7 hours:

image

and then:

image

As you can see, this Resource will work only 7 hours per day.

No I will assign Those Resources to Tasks:

image

Both, Task 1, and Task 2 has 10 days Duration, but the whole Project has 11,38 days of Duration. Why? Let’s look at the Task Usage View (I will make two Pictures):

image

As you can see Task 1 will be finished at Tuesday 31.3.2015 (two day later than Task 1).

Here is the second part of Task Usage View:

image

Both Task need 40 hours of work to be done! Why? Hit File Tab, then Options, and then:

image

So to finish each Task with 10 day Duration it will be needed for 80 hours (10 days * 8 hours per day)

Task 2 will be done with Resource who will work 8 hours per day, so it will start at Monday, and it will be Finished next Friday, because 80 hours = 80 / 8 hours per day = 10 days,

Task 1 will be done with Resource who will work 7 hours per day, so it will start at Monday, and it will be Finished at Tuesday after two weeks. Where the 11,38 days is coming from? If you look at the second picture form the Task Usage View, you will see that Resource – 7 hours per day will work 11 full days (7 hours per day), and at last day it will work only 3 hours, eg 3/8 = 0,38 days. So 11+0,38 = 11,38 days.

I know what you do not understand! Why is duration for Task 1 = 10 days! Frankly, I do not know. From my point of view  it should be 11,38

Now let’s look at the Detail View:

image

This is Fixed Units Task type.

But what if you want that both Task have 10 days duration, no matter who will work on them, and how many hours will someone work on them?

I will now change this to Task to Fixed Duration type:

image

Now Task has “right” Duration, but that is not what I want! I will change Duration to 10 days:

image

and I will get:

image

or / and (Second Picture):

image

It’s tricky, isn’t it?

Regards!

Advertisement

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, PMI, PRoject Management and tagged , , , , . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s