Tag Archives: Project Management; Scheduling Tasks

The “Wedding” Project! Building the Schedule? – PART 6 (YEAH! The LAST ONE)

  Hi, I will continue my last post! First, I will change the duration for the wedding night from 1hr to 12 hrs.: Now I will arrange my timescale: I want in middle Tier to have days: and in Bottom … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 3 Comments

The “Wedding” Project! Building the Schedule? – PART 5 (we are almost at the finish)

  Hi, In my previous post I have explained that Task no 6: “Call the guests by phone to the wedding” is a Predecessor of lot of other Tasks. I will again apply a filter to see those task: Because … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , | 4 Comments

The “Wedding” Project! Building the Schedule? – PART 4

  Hi, If you remember I had (and I still have) a problem with my “wedding” project. I set up a Wedding Saturday , and Wedding Sunday Task Calendars in MS PROJECT 2010. As I said many times before I … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 1 Comment

The “Wedding” Project! Building the Schedule? – PART 3

  Hi, In this blog post I will start to Create the schedule, and I will show you how can get in trouble when you do it. If you want to track this Blog post, and next few one, you … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 3 Comments

The “Wedding” Project! Building the Schedule? – PART 2

  Hi, this post might be very boring! Because I am using the “Wedding” project I will put duration for each and every task! There are 100 task and I had to explain why I put those duration for each … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 1 Comment

Develop a Scope for my Project! Is it easy or not?–PART 1

  Hi, In my last post I wrote about setting up the Project Environment. You can see that I did not set up any Calendar. Why? Well, there are different approaches to a Project Plan. My approach is to first … Continue reading

Posted in Microsoft PRoject 2010, PMI, PRoject Management | Tagged , , , , | Leave a comment

How to split tasks in MS PROJECT 2010

Hi, Suppose that you have a project with 5 tasks as is shown in the picture: Task 3 has a 3-day duration, and will start on Monday, 25.04.2011 and finish on Wednesday, 27.04.2011. What if your task can be done … Continue reading

Posted in Microsoft PRoject 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 6 Comments