Category Archives: Microsoft Project Server 2010

% Work Completed without Resources assigned to Tasks

  Hi, I wrote several Posts about % Work completed field, and how does it change when assigned Resources to the Task. As you know, Work is 0 hours until you assign Resource to the Task. But, is it possible … Continue reading

Posted in MICROSOFT PROJECT, Microsoft Project Server 2010, MS PROJECT 2016 | Tagged , , | Leave a comment

Maximal Units and Default Values in MS PROJECT 2013

Hi, my Blog Reader is in trouble. He wrote:”Hi Nenad, I am in need of a favor from you. I am currently working with the MS project to accomplish the team utilization and also to forecast the team’s availability. I … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 7 Comments

Multinational Calendars and how to use them in MS PROJECT 2013?

Hi, again, I have a question from one of my Blog readers: “Okay I have a question not certain if it belongs in this thread. I’m managing a project for resources in multiple locations using MS Project 2007: US and … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | Leave a comment

Bug in Tracking Gantt View in MS PROJECT 2013

Hi, here is another small bug in MS PROJECT 2013. I will Create few Tasks in MS PROJECT 2013: I want to see Critical Path, so I’m going to Use Tracking Gantt View: and I’ll get: On the Right side … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 3 Comments

BUG Resource-related Cost field not recalculated in MS PROJECT 2013

Hi, here is minor bug in MS PROJECT 2013, found by Eric Uyttewaal, my MVP friend. First I am going to create New Project with Single Task (1 day duration): I will now Create two Resources: Ted and Fred: Yu … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | 2 Comments

Task Calendar in MS PROJECT 2013 – when to use it?

Hi, Again, I have a request (question) from one of my Blog readers: ! “Hello, Your tutorials are very helpful – thank you! I was wondering if it is possible to make a particular task not allowed on a particular … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management | Tagged , , | Leave a comment

Inactive Tasks in MS PROJECT 2013

Hi, this Post will be a really short one! I’m going to explain how Inactive Task is different in MS PROJECT 2013. First, notice that this functionality is available only with MS PROJECT 2013 PROFESSIONAL version. I’ll create new Project,first: … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010 | Tagged , , | Leave a comment