Bug in Tracking Gantt View in MS PROJECT 2013

Hi,

here is another small bug in MS PROJECT 2013.

I will Create few Tasks in MS PROJECT 2013:

image

I want to see Critical Path, so I’m going to Use Tracking Gantt View:

image

and I’ll get:

image

On the Right side of the screen There is Critical Path (Red color). No I’m going to switch off Critical field from Bar Styles:

image 

and I’ll get:

image

Funny, isn’t it?

Advertisement

About Nenad Trajkovski

Location: Zagreb, Croatia Occupation: Project Manager Interests: Project Management and MS PROJECT He was born in Zagreb, Croatia at 1963. After completing his college he started working on projects in different business areas (banking, manufacturing, automotive industry, distribution, oil companies, etc.) developing and implementing ERP systems into different companies. He has got a lot of experience working with people in different business processes and also possesses great knowledge in information technologies and financial services. Today he works as a business consultant, adn Project Manager in PERPETUUM MOBILE d.o.o. Zagreb. He is a regular lecturer for Project Management in MS Innovation Center in Varaždin, Logosoft Sarajevo in Bosnia and Herzegovina and SEAVUS GROUP in Skopje Macedonia. He was named the best lecturer of WINDAYS 2008 while his lecture was also voted as the best. In addition, he was in TOP 10 lecturers at the MS SINERGY 2009 and MS VISIA 2009, 2010. Shares first place as the best lecturer of KulenDays 2009 and 2010 and PMI Conference 2009 in Zagreb. He is also a regular lecturer in the MS Community. He is a Certified Accountant and a PMP (Project Manager Professional) and a PMI-RMP (Risk Manager Professional), MCP, MCT, and Microsoft Certified Technical Specialist - Microsoft Project 2010. From 01.01.2012 awarded with MVP (Microsoft Most Valuable Proffesional - Microsoft Project)!
This entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, Microsoft Project Server 2010, MS PROJECT 2010, PMI, PRoject Management and tagged , , . Bookmark the permalink.

4 Responses to Bug in Tracking Gantt View in MS PROJECT 2013

  1. Emerson Carlos da Silva says:

    Yeah! Funny!
    The bug in the “Tracking Gantt View” continue in MS PROJECT 2016!

  2. Ray Lei says:

    got the same issue during software learning, how to fix it…….? thx.
    Tried to reinstall the project 2013, does not work….

  3. Dan Christopher says:

    Nenad,

    I have another possible bug in MSP 2013. Try this one
    Insert Date1, Insert Duration1, Insert Date2. Now go to custom fields and make date2 a formula [(date1)+(duration1). The obvious answer would be a new date, but this is what I get.

    Date1 Durat Date2
    Tue 7/8/14 0d Tue 7/8/14
    Tue 7/8/14 1d Sat 10/31/15
    Tue 7/8/14 2d Wed 2/22/17
    Tue 7/8/14 3d Sun 6/17/18
    Tue 7/8/14 4d Thu 10/10/19
    Tue 7/8/14 5d Mon 2/1/21

    it seems to move almost 14 months.

    Got any ideas on how to make this work?

    Thanks

    Dan

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s