-
Recent Posts
Archives
Categories
Blogroll
Tag Archives: MS – Calendars
Resources and Durations – how are they linked in MS PROJECT 2013!
Hi, very good friend of mine has a problem: “Nenad, please help me. I want to have some Resources with different working hours (for Example, John 1 hour per day, Mary 2 hours per day), and when I assign Single … Continue reading
Strange Duration in MS PROJECT 2013 – Bug or Not!
Hi, I will show you something that makes MS PROJECT users crazy! Of course I’ll use MS PROJECT 2013. I will first, create a Brand new Project with one Task with 5 days Duration, like this: Everything is just fine. … Continue reading
24 Hours Calendar – how it works in MS PROJECT 2013
Hi, I have a lot of questions about MS PROJECT 2013 Calendars, especially about 24 hours Calendar. I will explain how does it work in MS PROJECT 2013. First I will Create a very Simple Project with only one Task … Continue reading
Tracking resources exact hours on a standard calendar in MS PROJECT 2013
Hi, Again a question from one of my Blog readers: “Dear Nenad,I really appreciate your blog…helps me immensely.I would really be grateful if you could help me on tracking resources exact hours on a standard calendar. I am interested … Continue reading
How to apply multiple Resource Calendars to the Same Resource in MS PROJECT 2013?
Hi, my Blog reader has a problem: “My problem is that some of resources have 2 work schedules. When they work on-shore (5 days week 8 hours day) and off-shore (7 days week and 11 hours day), For each … Continue reading
Calendars and Moving Tasks to non working days in MS PROJECT 2013!
Hi, again I have a question from my Blog Reader: “I liked your article and thought you may have an answer to a question I have.In Project 2010 with tasks set to Auto schedule if you schedule the start … Continue reading
Task Calendars and Lag in MS PROJECT 2013
Hi, today I will answer to this question: “You have 2 tasks which own different task calendars (Standard 5day and 7day calendar). They are connected FS and have a lag, lets say 5 days. Which calendar does the lag use?” … Continue reading
How to make modified Calendar default for future Projects in MS PROJECT 2013!
Hi, here is the question from my Blog reader: “Is there a way to change the default calendar so that every new project is created with the predefined working time?” Let me show you how can you accomplish that! … Continue reading
How to Create Enterprise Calendars in MS PROJECT SERVER 2010!
Hi, In Enterprise environment, it is very important to create ENTERPRISE CALENDARS in MS PROJECT SERVER 2010! You should create working and non working hours, holidays, exceptions etc. To do that, I will open PWA, and I will get: … Continue reading
The “Wedding” Project! How to set up Calendars in MS PROJECT 2010, and why?–PART 1
Hi, As you know, from my previous posts, working time in MS PROJECT 2010 is set up in a Backstage view: and it says: When you put task duration in the Duration field in DAYS it will multiple days … Continue reading