Actual finish date in MS PROJECT 2013

  Hi, again, one of by Blog readers has a question: “How do you update actuals? Let’s say the task is supposed to have finished 21 Feb 2014 according to the original plan. However, this task can now be finished … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , , , | 4 Comments

% Complete VS Physical % Complete in MS PROJECT 2013

Hi, I will explain hot to track Physical % Complete in MS PROJECT 2013. In MS PROJECT you can Track %Complete, % Work Complete, and Physical % Complete. Where are the differences? % Complete is about Duration % Work Complete … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 10 Comments

Percentage completed vs. Actual Work in MS PROJECT 2013!

Hi, again, my Blog reader has a problem: “Dear Nenad, your blog is a real treasure and I am so happy I came across it a year ago when we started with the implementation of the MS Project Server 2010 … Continue reading

Posted in MICROSOFT PROJECT, Microsoft PRoject 2010, Microsoft Project 2013, MS PROJECT 2010, PMI, PRoject Management | Tagged , , , | 9 Comments