Tag Archives: Micorosft Project 2016 – Resources

Task Actual Start and Finish date when Resources are unavailable in MS PROJECT 2016

Hi, in this last post for year 2018. I will show you how Actual Start and Finish date are affected with Resource Calendar in MS PROJECT 2016. First I will crate Simple Project with one Task: I will create Two … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016 | Tagged , , | Leave a comment

How to hold Total Hours of work per Task when Actual Work is less then estimated hours in MS PROJECT 2016?

Hi, Today I’m going to explain how to solve a problem which one of my Blog Readers have in MS PROJECT 2016. Let us say that we have a Project with Task which is 6 weeks long. For this Task … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016 | Tagged , , | Leave a comment

How to change multiple Resources on Tasks in progress with MS PROJECT 2016?

Hi, today I will show you how to change multiple Resources when you have Tasks in progress with Microsoft Project 2016! Firs I’m going to create brand new Project with two simple Tasks: Now suppose that I have those Resources … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, PMI | Tagged , | Leave a comment

Additional Resources assigning to the Task which have work in progress in MS PROJECT 2016

Hi, Today I’m going to explain what happens if I assign additional resource in Task which has a progress with MS PROJECT 2016. First, I’m going to create brand new Project: I have two resources available: I will assign John … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2016, PMI | Tagged , , | Leave a comment

Inactive Tasks and Actuals in MS PROJECT 2016

Hi, I saw very interesting discussion in LinkedIn, about making Task Inactive if it has actuals. First let me show the “issue”. I will create brand new Project in MS PROJECT 2016: and I will create John as Resource with … Continue reading

Posted in MS PROJECT 2016 | Tagged , , , | Leave a comment

Over allocation not shown in MS PROJECT 2016 with Windows 10–Bug or not?

Hi, My blog reader has a problem. He explained it step by step, and I will answer at it in the same way. Project in certain instances doesn’t flag  over allocated resources.For example, I created a resource John and assigned … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | 1 Comment

Multiple assignments on the same Task in MS PROJECT 2016

  Hi, my Blog Reader has a very interesting question: “Hi Nenad I have a problem, and I hope you can help me, I’m a follower of your blog. I have some task on project and resources, but I want … Continue reading

Posted in MICROSOFT PROJECT, Micsrosoft Project 2016, MS PROJECT 2016, PMI, PRoject Management | Tagged , , , | Leave a comment

Resource with assignment 0%–what is it?

Hi, You can find a lot of examples when you can see that it is possible to assign Resource to Tasks with 0% Units. In this post I will show you how can you do it, and what would happen … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

How to automatically change Material relative to Scope change in MS PROJECT 2016

Hi, I’ve got very good question from one of my Blog readers: “Hi,I am a novice. Tried to find some solution to a certain scenario in your blogs but browsing through some dozen articles, I thought it better to ask … Continue reading

Posted in MICROSOFT PROJECT, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment

Assignment Delay field in MS PROJECT 2016

Hi, in Microsoft Project 2016 there is one very useful field called: Assignment Delay. Let me show you how useful is it, and how can you use it. First, as I always do, I will create simple Project: I will … Continue reading

Posted in Microsoft Project 2013, MS PROJECT 2016, PMI, PRoject Management | Tagged , , | Leave a comment